CPWD Analysis of Rates · Cladding Work
Providing and fixing expansion hold fasteners on C.C. /R.C.C./Brick masonry surface backing including drilling necessary holes and the cost of bolt etc complete. Wedge expansion type
Fastener with threaded dia 10 mm
- Item number
- 8.8.1.2
- Analysis basis
- Details of cost for 30nos. W.E.H. fastener
- Priced inputs
- 5
- Derived rate
- ₹40.00 / nos. W
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 8.8.1.2 — Providing and fixing expansion hold fasteners on C.C. /R.C.C./Brick masonry surface backing including drilling necessary holes and the cost of bolt etc complete. Wedge expansion type Fastener with threaded dia 10 mm — is derived from 5 priced inputs for 30nos. W and works out to ₹40.00 per nos. w after water charges, GST, CPOH and cess. The full build-up is below.
- 44.5mm length
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 7431 | Wedge expansion hold fastner 3/8” or 10 mm,Wedge expansion hold fastener 3/8” or 10 mmMaterial | each | 30 | 11.00 | 330.00 |
| 1034 | Bolts and nuts upto 300 mm in length (44.5+10mm)Bolts and nuts up to 300 mm in lengthMaterial | quintal | 0.006 | 5,200.00 | 31.20 |
| 0116 | Fitter (grade 1)Labour | day | 0.25 | 897.00 | 224.25 |
| 0114 | BeldarLabour | day | 0.25 | 736.00 | 184.00 |
| 9999 | Hire and running charges for hand drill machine Sundries, drilling bit scaffolding etcMaterial | L.S. | 32.5 | 2.27 | 73.78 |
- TOTAL
- 843.23
- Add 1 % Water charges on “W”
- 8.43
- TOTAL
- 851.66
- Add GST on “X” (multiplying factor 0.2127)
- 181.15
- TOTAL
- 1,032.81
- Add 15% CPOH on “Y”
- 154.92
- TOTAL
- 1,187.73
- Add Cess @ 1% on “Z”
- 11.88
- Cost for 30 nos.
- 1,199.61
- Cost of each
- 39.99
- Say
- 40.00
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 392. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works