Providing and fixing expansion hold fasteners on C.C. /R.C.C./Brick masonry surface backing including drilling necessary holes and the cost of bolt etc complete. Wedge expansion type

Fastener with threaded dia 10 mm
Item number
8.8.1.2
Analysis basis
30nos. W
Priced inputs
5
Derived rate
₹40.00/ NOS. W
D-01/RATE ANALYSISITEM 8.8.1.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 8.8.1.2 (Providing and fixing expansion hold fasteners on C.C. /R.C.C./Brick masonry surface backing including drilling necessary holes and the cost of bolt etc complete. Wedge expansion type Fastener with threaded dia 10 mm) is derived from 5 priced inputs for 30nos. W and works out to ₹40.00 per nos. w after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 44.5mm length
ANALYSIS OF RATES · ITEM 8.8.1.2DETAILS OF COST FOR 30NOS. W.E.H. FASTENER
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7431MATWedge expansion hold fastner 3/8” or 10 mm,Wedge expansion hold fastener 3/8” or 10 mmeach3011.00330.00
1034MATBolts and nuts upto 300 mm in length (44.5+10mm)Bolts and nuts up to 300 mm in lengthquintal0.0065,200.0031.20
0116LABFitter (grade 1)day0.25897.00224.25
0114LABBeldarday0.25736.00184.00
9999MATHire and running charges for hand drill machine Sundries, drilling bit scaffolding etcL.S.32.52.2773.78
BUILD-UP TO RATE
TOTAL
843.23
Add 1 % Water charges on “W”
+8.43
TOTAL
851.66
Add GST on “X” (multiplying factor 0.2127)
+181.15
TOTAL
1,032.81
Add 15% CPOH on “Y”
+154.92
TOTAL
1,187.73
Add Cess @ 1% on “Z”
+11.88
Cost for 30 nos.
1,199.61
Cost of each
39.99
SAY
₹40.00
D-02/SOURCEPRINTED PAGE 392
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
392

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 392. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.