Providing and fixing expansion hold fasteners on C.C. /R.C.C./Brick masonry surface backing including drilling necessary holes and the cost of bolt etc complete. Wedge expansion type
- Item number
- 8.8.1.1
- Analysis basis
- 300nos. W
- Priced inputs
- 5
- Derived rate
- ₹36.75/ NOS. W
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 8.8.1.1 (Providing and fixing expansion hold fasteners on C.C. /R.C.C./Brick masonry surface backing including drilling necessary holes and the cost of bolt etc complete. Wedge expansion type Fastener with threaded dia 6 mm) is derived from 5 priced inputs for 300nos. W and works out to ₹36.75 per nos. w after water charges, GST, CPOH and cess. The full build-up is below.
- 36.5mm length
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 7430 | MAT | Wedge expansion hold fastner 1/4” or 6 mm,Wedge expansion hold fastener 1/4” or 6 mm | each | 300 | 9.00 | 2,700.00 |
| 1034 | MAT | Bolts and nuts upto 300 mm in length (36.5+10mm)Bolts and nuts up to 300 mm in length | quintal | 0.045 | 5,200.00 | 234.00 |
| 0116 | LAB | Fitter (grade 1) | day | 2.5 | 897.00 | 2,242.50 |
| 0114 | LAB | Beldar | day | 2.5 | 736.00 | 1,840.00 |
| 9999 | MAT | Hire and running charges for hand drill machine Sundries, drilling bit scaffolding etc | L.S. | 325 | 2.27 | 737.75 |
- TOTAL
- 7,754.25
- Add 1 % Water charges on “W”
- +77.54
- TOTAL
- 7,831.79
- Add GST on “X” (multiplying factor 0.2127)
- +1,665.82
- TOTAL
- 9,497.61
- Add 15% CPOH on “Y”
- +1,424.64
- TOTAL
- 10,922.25
- Add Cess @ 1% on “Z”
- +109.22
- Cost for 300 nos.
- 11,031.47
- Cost of each
- 36.77
- SAY
- ₹36.75
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 391
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 391. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.