R/DAR 2023

Providing and fixing expansion hold fasteners on C.C. /R.C.C./Brick masonry surface backing including drilling necessary holes and the cost of bolt etc complete. Wedge expansion type

Fastener with threaded dia 6 mm
Item number
8.8.1.1
Analysis basis
300nos. W
Priced inputs
5
Derived rate
₹36.75/ NOS. W
D-01/RATE ANALYSISITEM 8.8.1.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 8.8.1.1 (Providing and fixing expansion hold fasteners on C.C. /R.C.C./Brick masonry surface backing including drilling necessary holes and the cost of bolt etc complete. Wedge expansion type Fastener with threaded dia 6 mm) is derived from 5 priced inputs for 300nos. W and works out to ₹36.75 per nos. w after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 36.5mm length
ANALYSIS OF RATES · ITEM 8.8.1.1DETAILS OF COST FOR 300NOS. W.E.H. FASTENER
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7430MATWedge expansion hold fastner 1/4” or 6 mm,Wedge expansion hold fastener 1/4” or 6 mmeach3009.002,700.00
1034MATBolts and nuts upto 300 mm in length (36.5+10mm)Bolts and nuts up to 300 mm in lengthquintal0.0455,200.00234.00
0116LABFitter (grade 1)day2.5897.002,242.50
0114LABBeldarday2.5736.001,840.00
9999MATHire and running charges for hand drill machine Sundries, drilling bit scaffolding etcL.S.3252.27737.75
BUILD-UP TO RATE
TOTAL
7,754.25
Add 1 % Water charges on “W”
+77.54
TOTAL
7,831.79
Add GST on “X” (multiplying factor 0.2127)
+1,665.82
TOTAL
9,497.61
Add 15% CPOH on “Y”
+1,424.64
TOTAL
10,922.25
Add Cess @ 1% on “Z”
+109.22
Cost for 300 nos.
11,031.47
Cost of each
36.77
SAY
₹36.75
D-02/SOURCEPRINTED PAGE 391
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
391

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 391. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.