CPWD Analysis of Rates · Cladding Work
Providing and fixing cramps of required size & shape in RCC/ CC / Brick masonry backing with cement mortar 1:2 ( 1 cement :2 coarse sand), including drilling necessary hole in stones and embedding the cramp in the hole (fastener to be paid separately)
Stainless steel cramps
- Item number
- 8.7.2
- Analysis basis
- Details of cost for 0.934 kg
- Priced inputs
- 4
- Derived rate
- ₹714.40 / kg
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 8.7.2 — Providing and fixing cramps of required size & shape in RCC/ CC / Brick masonry backing with cement mortar 1:2 ( 1 cement :2 coarse sand), including drilling necessary hole in stones and embedding the cramp in the hole (fastener to be paid separately) Stainless steel cramps — is derived from 4 priced inputs for 0.934 kg and works out to ₹714.40 per kg after water charges, GST, CPOH and cess. The full build-up is below.
- Stainless steel cramp
- 10 x 0.064 x 0.025 x 0.006 = 9.6 x 10^(-5)
- 10 x 0.025 x 0.025 x 0.006 = 3.7 x 10^(-5)
- = 13.3 x 10^(-5)
- 10^(-5)
- = 11.9 x 10^5 x 7850 = 0.934 kg
- Total = 0.981 kg.
- Cement mortar 1:2 (1 cement : 2 coarse sand)
- less hole 10 x 0.024 x 0.010 x 0.006 = 1.4 x
- Add wastage @ 5% = 0.047kg.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 7339 | Stainless steel crampMaterial | gram | 0.981 | 313.00 | 307.05 |
| 9977 | CarriageMaterial | L.S. | 3.9 | 2.27 | 8.85 |
| Rate as per Item Number 3.7 of SH: MortarsRate as per item 3.7Sub-analysis | cum | 0.001 | 5,584.50 | 5.58 | |
| 9999 | Labour for fixing in positionMaterial | L.S. | 65 | 2.27 | 147.55 |
- TOTAL
- 469.03
- Add 1 % Water charges on “W”
- 4.69
- TOTAL
- 473.72
- Add GST on “X” (multiplying factor 0.2127)
- 100.76
- TOTAL
- 574.48
- Add 15% CPOH on “Y”
- 86.17
- TOTAL
- 660.65
- Add Cess @ 1% on “Z”
- 6.61
- Cost for 0.934 kg.
- 667.26
- Cost per kg
- 714.41
- Say
- 714.40
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 391. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.