CPWD Analysis of Rates · Cladding Work

Providing and fixing cramps of required size & shape in RCC/ CC / Brick masonry backing with cement mortar 1:2 ( 1 cement :2 coarse sand), including drilling necessary hole in stones and embedding the cramp in the hole (fastener to be paid separately)

Stainless steel cramps

Item number
8.7.2
Analysis basis
Details of cost for 0.934 kg
Priced inputs
4
Derived rate
714.40 / kg

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 8.7.2 Providing and fixing cramps of required size & shape in RCC/ CC / Brick masonry backing with cement mortar 1:2 ( 1 cement :2 coarse sand), including drilling necessary hole in stones and embedding the cramp in the hole (fastener to be paid separately) Stainless steel cramps — is derived from 4 priced inputs for 0.934 kg and works out to ₹714.40 per kg after water charges, GST, CPOH and cess. The full build-up is below.

  • Stainless steel cramp
  • 10 x 0.064 x 0.025 x 0.006 = 9.6 x 10^(-5)
  • 10 x 0.025 x 0.025 x 0.006 = 3.7 x 10^(-5)
  • = 13.3 x 10^(-5)
  • 10^(-5)
  • = 11.9 x 10^5 x 7850 = 0.934 kg
  • Total = 0.981 kg.
  • Cement mortar 1:2 (1 cement : 2 coarse sand)
  • less hole 10 x 0.024 x 0.010 x 0.006 = 1.4 x
  • Add wastage @ 5% = 0.047kg.
CodeInputUnitQuantityRate (INR)Amount (INR)
7339Stainless steel crampMaterialgram0.981313.00307.05
9977CarriageMaterialL.S.3.92.278.85
Rate as per Item Number 3.7 of SH: MortarsRate as per item 3.7Sub-analysiscum0.0015,584.505.58
9999Labour for fixing in positionMaterialL.S.652.27147.55
TOTAL
469.03
Add 1 % Water charges on “W”
4.69
TOTAL
473.72
Add GST on “X” (multiplying factor 0.2127)
100.76
TOTAL
574.48
Add 15% CPOH on “Y”
86.17
TOTAL
660.65
Add Cess @ 1% on “Z”
6.61
Cost for 0.934 kg.
667.26
Cost per kg
714.41
Say
714.40

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 391. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.