Providing and fixing stone slab with table rubbed, edges rounded and polished, of size 75x50 cm deep and 1.8 cm thick, fixed in urinal partitions by cutting a chase of appropriate width with chase cutter and embedding the stone in the chase with epoxy grout or with cement concrete

1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 6 mm nominal size) as per direction of Engineer-in-charge and finished smooth. White Agaria Marble Stone

Item number
8.10.1
Analysis basis
Details of cost for one No or 0.375 sqm.
Priced inputs
4
Derived rate
3,500.45 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 8.10.1 Providing and fixing stone slab with table rubbed, edges rounded and polished, of size 75x50 cm deep and 1.8 cm thick, fixed in urinal partitions by cutting a chase of appropriate width with chase cutter and embedding the stone in the chase with epoxy grout or with cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 6 mm nominal size) as per direction of Engineer-in-charge and finished smooth. White Agaria Marble Stone — is derived from 4 priced inputs for one No and works out to ₹3,500.45 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • Agaria Marble Stone 1 X 0.75 X 0.50 =0.375
  • sqm+Add wastage 20% = 0.075 sqm. Total =
  • 0.45sqm.
CodeInputUnitQuantityRate (INR)Amount (INR)
7244Table rubbed polished stone 18 mm thick (75x50cm) Agaria Marble stone - 18 mm thickMaterialsqm0.451,615.00726.75
9999Cement concrete 1:2:4 for fillingMaterialL.S.21.582.2748.99
9999Labour for fixing, edge rounding and final polishingMaterialL.S.43.162.2797.97
9999SundriesMaterialL.S.21.582.2748.99
TOTAL
922.70
Add 1 % Water charges on “W”
9.23
TOTAL
931.93
Add GST on “X” (multiplying factor 0.2127)
198.22
TOTAL
1,130.15
Add 15% CPOH on “Y”
169.52
TOTAL
1,299.67
Add Cess @ 1% on “Z”
13.00
Cost of 0.375sqm
1,312.67
Cost of 1.00 sqm
3,500.45
Say
3,500.45

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 394. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.