Extra for fixing marble /granite stone, over and above corresponding basic item, in facia and drops of width upto 150 mm with epoxy resin based adhesive, including cleaning etc. complete

Item number
8.4
Analysis basis
facia 1
Priced inputs
4
Derived rate
₹568.55/ FACIA 1
D-01/RATE ANALYSISITEM 8.4

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 8.4 (Extra for fixing marble /granite stone, over and above corresponding basic item, in facia and drops of width upto 150 mm with epoxy resin based adhesive, including cleaning etc. complete) is derived from 4 priced inputs for facia 1 and works out to ₹568.55 per facia 1 after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • wide
  • Cement mortar 1 : 4 (1 cement :4 coarse sand)
  • 1.5x0.15x0.02 = 0.005cum.
ANALYSIS OF RATES · ITEM 8.4DETAILS OF COST FOR FACIA 1.5M LONG AND 0.15M
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0123LABMason 1st classMason 1st classday0.3897.00269.10
0115LABCoolieday0.3736.00220.80
9999MATScaffolding, expoxyL.S.392.2788.53
SUBRate as per Item Number 3.9 of SH: MortarsRate as per item 3.9cum0.0054,211.7021.06
BUILD-UP TO RATE
TOTAL
599.49
Add 1 % Water charges on “W”
+5.99
TOTAL
605.48
Add GST on “X” (multiplying factor 0.2127)
+128.79
TOTAL
734.27
Add 15% CPOH on “Y”
+110.14
TOTAL
844.41
Add Cess @ 1% on “Z”
+8.44
Cost for 1.5 metre
852.85
Cost per metre
568.57
SAY
₹568.55
D-02/SOURCEPRINTED PAGE 389
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
389

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 389. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.