Extra for providing opening of required size & shape for wash basin/ kitchen sink in kitchen platform, vanity counter and similar location in marble/ Granite/ stone work, including necessary holes for pillar taps etc. including moulding, rubbing and polishing of cut edges etc. complete

Item number
8.5
Analysis basis
providing an
Priced inputs
3
Derived rate
₹978.70/ PROVIDING AN
D-01/RATE ANALYSISITEM 8.5

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 8.5 (Extra for providing opening of required size & shape for wash basin/ kitchen sink in kitchen platform, vanity counter and similar location in marble/ Granite/ stone work, including necessary holes for pillar taps etc. including moulding, rubbing and polishing of cut edges etc. complete) is derived from 3 priced inputs for providing an and works out to ₹978.70 per providing an after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • quired size and shape
ANALYSIS OF RATES · ITEM 8.5DETAILS OF COST FOR PROVIDING AN OPENING OF RE-
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0126LABMason (for ornamental stone work) 1st classday0.4897.00358.80
0114LABBeldarday0.4736.00294.40
9999MATSundriesL.S.15.32.2734.73
BUILD-UP TO RATE
TOTAL
687.93
Add 1 % Water charges on “W”
+6.88
TOTAL
694.81
Add GST on “X” (multiplying factor 0.2127)
+147.79
TOTAL
842.60
Add 15% CPOH on “Y”
+126.39
TOTAL
968.99
Add Cess @ 1% on “Z”
+9.69
Cost of each
978.68
SAY
₹978.70
D-02/SOURCEPRINTED PAGE 389
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
389

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 389. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSCLADDING WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.