Skip to main content

CPWD Analysis of Rates · Cladding Work

Providing edge moulding to 18 mm thick marble stone counters, Vanities etc., including machine polishing to edge to give high gloss finish etc. complete as per design approved by Engineerin-Charge

Granite work

Item number
8.3.2
Analysis basis
Details of cost for 10.00 m
Priced inputs
3
Derived rate
510.95 / m

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 8.3.2 Providing edge moulding to 18 mm thick marble stone counters, Vanities etc., including machine polishing to edge to give high gloss finish etc. complete as per design approved by Engineerin-Charge Granite work — is derived from 3 priced inputs for 10.00 m and works out to ₹510.95 per m after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
0019Hand Grinder For mirror polishMachineryday2.5300.00750.00
0114BeldarLabourday3.5736.002,576.00
9999Sundries Blades & Polished etc.MaterialL.S.1172.27265.59
TOTAL
3,591.59
Add 1 % Water charges on “W”
35.92
TOTAL
3,627.51
Add GST on “X” (multiplying factor 0.2127)
771.57
TOTAL
4,399.08
Add 15% CPOH on “Y”
659.86
TOTAL
5,058.94
Add Cess @ 1% on “Z”
50.59
Cost for 10 metre
5,109.53
Cost per metre
510.95
Say
510.95

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 388. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works