Providing edge moulding to 18 mm thick marble stone counters, Vanities etc., including machine polishing to edge to give high gloss finish etc. complete as per design approved by Engineerin-Charge

Marble work
Item number
8.3.1
Analysis basis
10.00 m
Priced inputs
3
Derived rate
₹298.60/ M
D-01/RATE ANALYSISITEM 8.3.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 8.3.1 (Providing edge moulding to 18 mm thick marble stone counters, Vanities etc., including machine polishing to edge to give high gloss finish etc. complete as per design approved by Engineerin-Charge Marble work) is derived from 3 priced inputs for 10.00 m and works out to ₹298.60 per m after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 8.3.1DETAILS OF COST FOR 10.00 M
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0019MACHHand Grinder For mirror polishday1.5300.00450.00
0114LABBeldarday2736.001,472.00
9999MATSundries Blades & Polished etc.L.S.782.27177.06
BUILD-UP TO RATE
TOTAL
2,099.06
Add 1 % Water charges on “W”
+20.99
TOTAL
2,120.05
Add GST on “X” (multiplying factor 0.2127)
+450.93
TOTAL
2,570.98
Add 15% CPOH on “Y”
+385.65
TOTAL
2,956.63
Add Cess @ 1% on “Z”
+29.57
Cost for 10 metre
2,986.20
Cost per metre
298.62
SAY
₹298.60
D-02/SOURCEPRINTED PAGE 388
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
388

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 388. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.