CPWD Analysis of Rates · Cladding Work
Providing edge moulding to 18 mm thick marble stone counters, Vanities etc., including machine polishing to edge to give high gloss finish etc. complete as per design approved by Engineerin-Charge
Marble work
- Item number
- 8.3.1
- Analysis basis
- Details of cost for 10.00 m
- Priced inputs
- 3
- Derived rate
- ₹298.60 / m
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 8.3.1 — Providing edge moulding to 18 mm thick marble stone counters, Vanities etc., including machine polishing to edge to give high gloss finish etc. complete as per design approved by Engineerin-Charge Marble work — is derived from 3 priced inputs for 10.00 m and works out to ₹298.60 per m after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0019 | Hand Grinder For mirror polishMachinery | day | 1.5 | 300.00 | 450.00 |
| 0114 | BeldarLabour | day | 2 | 736.00 | 1,472.00 |
| 9999 | Sundries Blades & Polished etc.Material | L.S. | 78 | 2.27 | 177.06 |
- TOTAL
- 2,099.06
- Add 1 % Water charges on “W”
- 20.99
- TOTAL
- 2,120.05
- Add GST on “X” (multiplying factor 0.2127)
- 450.93
- TOTAL
- 2,570.98
- Add 15% CPOH on “Y”
- 385.65
- TOTAL
- 2,956.63
- Add Cess @ 1% on “Z”
- 29.57
- Cost for 10 metre
- 2,986.20
- Cost per metre
- 298.62
- Say
- 298.60
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 388. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.