Skip to main content
R/DAR 2023

Providing and fixing skirting with Pre-laminated (one side decorative and other side balancing lamination) flat pressed 3 layer or graded particle board (medium density) Grade I, Type II, IS :12823 marked, with necessary fixing arrangements and screws, including drilling necessary holes for rawl plugs etc. and priming coat on unexposed surface complete

18 mm thick
Item number
8.30.1
Analysis basis
skirting 200mm
Priced inputs
8
Derived rate
₹1,976.45/ SQM
D-01/RATE ANALYSISITEM 8.30.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 8.30.1 (Providing and fixing skirting with Pre-laminated (one side decorative and other side balancing lamination) flat pressed 3 layer or graded particle board (medium density) Grade I, Type II, IS :12823 marked, with necessary fixing arrangements and screws, including drilling necessary holes for rawl plugs etc. and priming coat on unexposed surface complete : 18 mm thick) is derived from 8 priced inputs for skirting 200mm and works out to ₹1,976.45 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • long Area = 0.2x30= 6 sqm.
  • Area = 0.2x30= 6 sqm.
  • Teak shade prelaminated Particle board (three
  • layer medium density) = 6.0 sqm.+
  • Total = 6.6 sqm.
  • For dressing and fixing particle board to skirting
  • Painting with ready mixed priming coat at back
  • Add wastage @ 10% = 0.6sqm.
ANALYSIS OF RATES · ITEM 8.30.1DETAILS OF COST FOR SKIRTING 200MM WIDE AND 30M
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7478MATPrelaminated particle board with one side decorative and other side balancing lamination, flat pressed 3 layer & graded (medium density) Grade I, Type II conforming to IS : 12823 (exterior grade) 18 mm thickPrelaminated flat pressed three layer or graded wood particle board with one side decorative and other side balancing lamination, (medium density) Grade I, Type II conforming and marked to IS : 12823 (exterior grade) 18 mm thicksqm6.6590.003,894.00
9977MATCarriage of particle boardL.S.8.112.2718.41
7048MATRawl plug 50 mm (designation 10 no.)Rawl plug 50 mm (designation 10)each10224.002,448.00
9999MATLabour for drilling holesL.S.1302.27295.10
0112LABCarpenter 2nd classday0.77816.00628.32
0114LABBeldarday0.86736.00632.96
9999MATSundries (Screws, sand paper)L.S.53.822.27122.17
SUBRate as per item no 13.85.1 of SH : FinishingRate as per item 13.85.1sqm670.35422.10
BUILD-UP TO RATE
TOTAL
8,461.06
Add 1 % Water charges on “W-A”
+80.39
TOTAL
8,541.45
Add GST on “X-A” (multiplying factor 0.2127)
+1,726.99
TOTAL
10,268.44
Add 15% CPOH on “Y-A”
+1,476.95
TOTAL
11,745.39
Add Cess @ 1% on “Z-A”
+113.23
Cost of 6 sqm.
11,858.62
Cost of 1 sqm.
1,976.44
SAY
₹1,976.45
D-02/SOURCEPRINTED PAGE 429
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
429

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 429. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSCLADDING WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.