Skip to main content
R/DAR 2023

Providing and fixing plywood 4 mm thick, one side decorative veneer conforming to IS: 1328 (type-1), for plain lining / cladding with necessary screws, including priming coat on unexposed surface with

Decorative veneer facings of approved manufacture
Item number
8.28.1
Analysis basis
Details of cost for 10sqm.
Priced inputs
8
Derived rate
₹1,946.25/ SQM
D-01/RATE ANALYSISITEM 8.28.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 8.28.1 (Providing and fixing plywood 4 mm thick, one side decorative veneer conforming to IS: 1328 (type-1), for plain lining / cladding with necessary screws, including priming coat on unexposed surface with : Decorative veneer facings of approved manufacture) is derived from 8 priced inputs and works out to ₹1,946.25 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Teak ply wood = 10sqm.
  • Total = 12 sqm.
  • Second class teak wood plugs including cutting
  • brick work and fixing in cement mortar 1:3 (1
  • cement: 3 fine sand)
  • Painting with ready mixed priming coat
  • Add for wastage @ 20% = 2 sqm.
ANALYSIS OF RATES · ITEM 8.28.1DETAILS OF COST FOR 10SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0759MATDecorative plywood 4 mmsqm12345.004,140.00
9977MATCarriage of ply woodL.S.5.462.2712.39
SUBRate as per item no 8.23 of SH : Cladding WorkRate as per item 8.23each5540.852,246.75
0111LABCarpenter 1st classday3.8897.003,408.60
0114LABBeldarday4.6736.003,385.60
0130LABMistryday0.6897.00538.20
9999MAT20mm nails without head for fixing plyL.S.53.822.27122.17
SUBRate as per item no 13.85.1 of SH : FinishingRate as per item 13.85.1sqm1070.35703.50
BUILD-UP TO RATE
TOTAL
14,557.21
Add 1 % Water charges on “W-A”
+116.07
TOTAL
14,673.28
Add GST on “X-A” (multiplying factor 0.2127)
+2,493.49
TOTAL
17,166.77
Add 15% CPOH on “Y-A”
+2,132.48
TOTAL
19,299.25
Add Cess @ 1% on “Z-A”
+163.49
Cost of 10 sqm.
19,462.74
Cost of 1 sqm.
1,946.27
SAY
₹1,946.25
D-02/SOURCEPRINTED PAGE 427
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
427

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 427. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSCLADDING WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.