Providing and fixing plywood 4 mm thick, one side decorative veneer conforming to IS: 1328 (type-1), for plain lining / cladding with necessary screws, including priming coat on unexposed surface with
- Item number
- 8.28.1
- Analysis basis
- Details of cost for 10sqm.
- Priced inputs
- 8
- Derived rate
- ₹1,946.25/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 8.28.1 (Providing and fixing plywood 4 mm thick, one side decorative veneer conforming to IS: 1328 (type-1), for plain lining / cladding with necessary screws, including priming coat on unexposed surface with : Decorative veneer facings of approved manufacture) is derived from 8 priced inputs and works out to ₹1,946.25 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Teak ply wood = 10sqm.
- Total = 12 sqm.
- Second class teak wood plugs including cutting
- brick work and fixing in cement mortar 1:3 (1
- cement: 3 fine sand)
- Painting with ready mixed priming coat
- Add for wastage @ 20% = 2 sqm.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0759 | MAT | Decorative plywood 4 mm | sqm | 12 | 345.00 | 4,140.00 |
| 9977 | MAT | Carriage of ply wood | L.S. | 5.46 | 2.27 | 12.39 |
| SUB | Rate as per item no 8.23 of SH : Cladding WorkRate as per item 8.23 | each | 55 | 40.85 | 2,246.75 | |
| 0111 | LAB | Carpenter 1st class | day | 3.8 | 897.00 | 3,408.60 |
| 0114 | LAB | Beldar | day | 4.6 | 736.00 | 3,385.60 |
| 0130 | LAB | Mistry | day | 0.6 | 897.00 | 538.20 |
| 9999 | MAT | 20mm nails without head for fixing ply | L.S. | 53.82 | 2.27 | 122.17 |
| SUB | Rate as per item no 13.85.1 of SH : FinishingRate as per item 13.85.1 | sqm | 10 | 70.35 | 703.50 |
- TOTAL
- 14,557.21
- Add 1 % Water charges on “W-A”
- +116.07
- TOTAL
- 14,673.28
- Add GST on “X-A” (multiplying factor 0.2127)
- +2,493.49
- TOTAL
- 17,166.77
- Add 15% CPOH on “Y-A”
- +2,132.48
- TOTAL
- 19,299.25
- Add Cess @ 1% on “Z-A”
- +163.49
- Cost of 10 sqm.
- 19,462.74
- Cost of 1 sqm.
- 1,946.27
- SAY
- ₹1,946.25
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 427
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 427. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.