CPWD Analysis of Rates · Cladding Work

Providing and fixing plywood 4 mm thick, one side decorative veneer conforming to IS: 1328 (type-1), for plain lining / cladding with necessary screws, including priming coat on unexposed surface with

Decorative veneer facings of approved manufacture

Item number
8.28.1
Analysis basis
Details of cost for 10sqm.
Priced inputs
8
Derived rate
1,946.25 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 8.28.1 Providing and fixing plywood 4 mm thick, one side decorative veneer conforming to IS: 1328 (type-1), for plain lining / cladding with necessary screws, including priming coat on unexposed surface with : Decorative veneer facings of approved manufacture — is derived from 8 priced inputs and works out to ₹1,946.25 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • Teak ply wood = 10sqm.
  • Total = 12 sqm.
  • Second class teak wood plugs including cutting
  • brick work and fixing in cement mortar 1:3 (1
  • cement: 3 fine sand)
  • Painting with ready mixed priming coat
  • Add for wastage @ 20% = 2 sqm.
CodeInputUnitQuantityRate (INR)Amount (INR)
0759Decorative plywood 4 mmMaterialsqm12345.004,140.00
9977Carriage of ply woodMaterialL.S.5.462.2712.39
Rate as per item no 8.23 of SH : Cladding WorkRate as per item 8.23Sub-analysiseach5540.852,246.75
0111Carpenter 1st classLabourday3.8897.003,408.60
0114BeldarLabourday4.6736.003,385.60
0130MistryLabourday0.6897.00538.20
999920mm nails without head for fixing plyMaterialL.S.53.822.27122.17
Rate as per item no 13.85.1 of SH : FinishingRate as per item 13.85.1Sub-analysissqm1070.35703.50
TOTAL
14,557.21
Add 1 % Water charges on “W-A”
116.07
TOTAL
14,673.28
Add GST on “X-A” (multiplying factor 0.2127)
2,493.49
TOTAL
17,166.77
Add 15% CPOH on “Y-A”
2,132.48
TOTAL
19,299.25
Add Cess @ 1% on “Z-A”
163.49
Cost of 10 sqm.
19,462.74
Cost of 1 sqm.
1,946.27
Say
1,946.25

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 427. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.