CPWD Analysis of Rates · Cladding Work

Providing and fixing 2nd class teak wood plain lining tongued and grooved, including wooden plugs complete with necessary screws and priming coat on unexposed surface

20 mm thick

Item number
8.25.3
Analysis basis
Details of cost of 10 sqm
Priced inputs
8
Derived rate
3,601.30 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 8.25.3 Providing and fixing 2nd class teak wood plain lining tongued and grooved, including wooden plugs complete with necessary screws and priming coat on unexposed surface 20 mm thick — is derived from 8 priced inputs and works out to ₹3,601.30 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • Teak wood (2nd class) 10x0.02m = 0.20cum.+
  • Total = 0.22 cum. Say 220 cudm.
  • Priming coat
  • Add wastage @ 10% = 0.02 cum.
CodeInputUnitQuantityRate (INR)Amount (INR)
1190Second class teak wood in planksMaterialcudm22791.0017,402.00
1231Extra for selected planks of second class teakwoodMaterialcudm22150.003,300.00
Rate as per item no 8.23 of SH : Cladding WorkRate as per item 8.23Sub-analysiseach5540.852,246.75
Rate as per item no 13.85.1 of SH : FinishingRate as per item 13.85.1Sub-analysissqm1070.35703.50
0111Carpenter 1st classLabourday1.08897.00968.76
0112Carpenter 2nd classLabourday0.8816.00652.80
0114BeldarLabourday1.08736.00794.88
9999Sundries & screws etc.MaterialL.S.53.822.27122.17
TOTAL
26,190.86
Add 1 % Water charges on “W-A”
232.41
TOTAL
26,423.27
Add GST on “X-A” (multiplying factor 0.2127)
4,992.71
TOTAL
31,415.98
Add 15% CPOH on “Y-A”
4,269.86
TOTAL
35,685.84
Add Cess @ 1% on “Z-A”
327.36
Cost of 10 sqm.
36,013.20
Cost of 1 sqm.
3,601.32
Say
3,601.30

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 423. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.