R/DAR 2023

Providing and fixing 2nd class teak wood plain lining tongued and grooved, including wooden plugs complete with necessary screws and priming coat on unexposed surface

20 mm thick
Item number
8.25.3
Analysis basis
Details of cost of 10 sqm
Priced inputs
8
Derived rate
₹3,601.30/ SQM
D-01/RATE ANALYSISITEM 8.25.3

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 8.25.3 (Providing and fixing 2nd class teak wood plain lining tongued and grooved, including wooden plugs complete with necessary screws and priming coat on unexposed surface 20 mm thick) is derived from 8 priced inputs and works out to ₹3,601.30 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Teak wood (2nd class) 10x0.02m = 0.20cum.+
  • Total = 0.22 cum. Say 220 cudm.
  • Priming coat
  • Add wastage @ 10% = 0.02 cum.
ANALYSIS OF RATES · ITEM 8.25.3DETAILS OF COST OF 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1190MATSecond class teak wood in plankscudm22791.0017,402.00
1231MATExtra for selected planks of second class teakwoodcudm22150.003,300.00
SUBRate as per item no 8.23 of SH : Cladding WorkRate as per item 8.23each5540.852,246.75
SUBRate as per item no 13.85.1 of SH : FinishingRate as per item 13.85.1sqm1070.35703.50
0111LABCarpenter 1st classday1.08897.00968.76
0112LABCarpenter 2nd classday0.8816.00652.80
0114LABBeldarday1.08736.00794.88
9999MATSundries & screws etc.L.S.53.822.27122.17
BUILD-UP TO RATE
TOTAL
26,190.86
Add 1 % Water charges on “W-A”
+232.41
TOTAL
26,423.27
Add GST on “X-A” (multiplying factor 0.2127)
+4,992.71
TOTAL
31,415.98
Add 15% CPOH on “Y-A”
+4,269.86
TOTAL
35,685.84
Add Cess @ 1% on “Z-A”
+327.36
Cost of 10 sqm.
36,013.20
Cost of 1 sqm.
3,601.32
SAY
₹3,601.30
D-02/SOURCEPRINTED PAGE 423
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
423

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 423. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.