Providing and fixing 2nd class teak wood plain lining tongued and grooved, including wooden plugs complete with necessary screws and priming coat on unexposed surface
- Item number
- 8.25.3
- Analysis basis
- Details of cost of 10 sqm
- Priced inputs
- 8
- Derived rate
- ₹3,601.30/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 8.25.3 (Providing and fixing 2nd class teak wood plain lining tongued and grooved, including wooden plugs complete with necessary screws and priming coat on unexposed surface 20 mm thick) is derived from 8 priced inputs and works out to ₹3,601.30 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Teak wood (2nd class) 10x0.02m = 0.20cum.+
- Total = 0.22 cum. Say 220 cudm.
- Priming coat
- Add wastage @ 10% = 0.02 cum.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 1190 | MAT | Second class teak wood in planks | cudm | 22 | 791.00 | 17,402.00 |
| 1231 | MAT | Extra for selected planks of second class teakwood | cudm | 22 | 150.00 | 3,300.00 |
| SUB | Rate as per item no 8.23 of SH : Cladding WorkRate as per item 8.23 | each | 55 | 40.85 | 2,246.75 | |
| SUB | Rate as per item no 13.85.1 of SH : FinishingRate as per item 13.85.1 | sqm | 10 | 70.35 | 703.50 | |
| 0111 | LAB | Carpenter 1st class | day | 1.08 | 897.00 | 968.76 |
| 0112 | LAB | Carpenter 2nd class | day | 0.8 | 816.00 | 652.80 |
| 0114 | LAB | Beldar | day | 1.08 | 736.00 | 794.88 |
| 9999 | MAT | Sundries & screws etc. | L.S. | 53.82 | 2.27 | 122.17 |
- TOTAL
- 26,190.86
- Add 1 % Water charges on “W-A”
- +232.41
- TOTAL
- 26,423.27
- Add GST on “X-A” (multiplying factor 0.2127)
- +4,992.71
- TOTAL
- 31,415.98
- Add 15% CPOH on “Y-A”
- +4,269.86
- TOTAL
- 35,685.84
- Add Cess @ 1% on “Z-A”
- +327.36
- Cost of 10 sqm.
- 36,013.20
- Cost of 1 sqm.
- 3,601.32
- SAY
- ₹3,601.30
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 423
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 423. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.