CPWD Analysis of Rates · Cladding Work
Providing and fixing 2nd class teak wood plain lining tongued and grooved, including wooden plugs complete with necessary screws and priming coat on unexposed surface
25 mm thick
- Item number
- 8.25.2
- Analysis basis
- Details of cost of 10 sqm
- Priced inputs
- 7
- Derived rate
- ₹4,437.80 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 8.25.2 — Providing and fixing 2nd class teak wood plain lining tongued and grooved, including wooden plugs complete with necessary screws and priming coat on unexposed surface 25 mm thick — is derived from 7 priced inputs and works out to ₹4,437.80 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Teak wood 2nd class 10x0.25 = 0.25cum+
- Total = 0.275 cum. Say 275 cudm.
- Priming coat
- Add wastage @ 10% = 0.025 cum.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 1190 | Second class teak wood in planksMaterial | cudm | 27.5 | 791.00 | 21,752.50 |
| 1231 | Extra for selected planks of second class teakwoodMaterial | cudm | 27.5 | 150.00 | 4,125.00 |
| Rate as per item no 8.23 of SH : Cladding WorkRate as per item 8.23Sub-analysis | each | 55 | 40.85 | 2,246.75 | |
| Rate as per item no 13.85.1 of SH : FinishingRate as per item 13.85.1Sub-analysis | sqm | 10 | 70.35 | 703.50 | |
| 0111 | Carpenter 1st classLabour | day | 2.15 | 897.00 | 1,928.55 |
| 0114 | BeldarLabour | day | 1.62 | 736.00 | 1,192.32 |
| 9999 | Sundries & screws etc.Material | L.S. | 53.82 | 2.27 | 122.17 |
- TOTAL
- 32,070.79
- Add 1 % Water charges on “W-A”
- 291.21
- TOTAL
- 32,362.00
- Add GST on “X-A” (multiplying factor 0.2127)
- 6,255.88
- TOTAL
- 38,617.88
- Add 15% CPOH on “Y-A”
- 5,350.14
- TOTAL
- 43,968.02
- Add Cess @ 1% on “Z-A”
- 410.18
- Cost of 10 sqm.
- 44,378.20
- Cost of 1 sqm.
- 4,437.82
- Say
- 4,437.80
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 423. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.