CPWD Analysis of Rates · Cladding Work

Providing and fixing 2nd class teak wood plain lining tongued and grooved, including wooden plugs complete with necessary screws and priming coat on unexposed surface

40 mm thick

Item number
8.25.1
Analysis basis
Details of cost of 10 sqm
Priced inputs
7
Derived rate
6,646.70 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 8.25.1 Providing and fixing 2nd class teak wood plain lining tongued and grooved, including wooden plugs complete with necessary screws and priming coat on unexposed surface 40 mm thick — is derived from 7 priced inputs and works out to ₹6,646.70 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • Teak wood (2nd class) 10x0.04m = 0.40cum+
  • Total = 0.44 cum. Say 440 cudm.
  • Second class teak wood plugs including cutting
  • brick work and fixing in cement mortar 1:3 (1
  • cement : 3 fine sand)
  • Priming coat
  • Add wastage @ 10% = 0.04 cum.
CodeInputUnitQuantityRate (INR)Amount (INR)
1190Second class teak wood in planksMaterialcudm44791.0034,804.00
1231Extra for selected planks of second class teakwoodMaterialcudm44150.006,600.00
Rate as per item no 8.23 of SH : Cladding WorkRate as per item 8.23Sub-analysiseach5540.852,246.75
Rate as per item no 13.85.1 of SH : FinishingRate as per item 13.85.1Sub-analysissqm1070.35703.50
0111Carpenter 1st classLabourday2.15897.001,928.55
0114BeldarLabourday1.62736.001,192.32
9999Sundries & screws etc.MaterialL.S.53.822.27122.17
TOTAL
47,597.29
Add 1 % Water charges on “W-A”
446.47
TOTAL
48,043.76
Add GST on “X-A” (multiplying factor 0.2127)
9,591.39
TOTAL
57,635.15
Add 15% CPOH on “Y-A”
8,202.74
TOTAL
65,837.89
Add Cess @ 1% on “Z-A”
628.88
Cost of 10 sqm.
66,466.77
Cost of 1 sqm.
6,646.68
Say
6,646.70

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 422. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.