Skip to main content

CPWD Analysis of Rates · Cladding Work

Providing and fixing dry cladding upto 10 metre heights with 30mm thick gang saw cut stone

with machine cut edges of uniform colour and size upto 1mx1m, fixed to structural steel frame work and/ or with the help of cramps, pins etc. and sealing the joints with approved weather sealant as per Architectural drawing and direction of Engineer-in-charge. (The steel frame work, stainless steel cramps and pins etc. shall be paid for separately). Red sand stone - 30mm thick gang saw cut stone

Item number
8.20.1
Analysis basis
Details of cost for 1 sqm.
Priced inputs
9
Derived rate
2,902.65 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 8.20.1 Providing and fixing dry cladding upto 10 metre heights with 30mm thick gang saw cut stone with machine cut edges of uniform colour and size upto 1mx1m, fixed to structural steel frame work and/ or with the help of cramps, pins etc. and sealing the joints with approved weather sealant as per Architectural drawing and direction of Engineer-in-charge. (The steel frame work, stainless steel cramps and pins etc. shall be paid for separately). Red sand stone - 30mm thick gang saw cut stone — is derived from 9 priced inputs for 1 sqm and works out to ₹2,902.65 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • Red sand stone = 1.00sqm. Add 5% wastage =
  • 0.05sqm. Total = 1.05 sqm
CodeInputUnitQuantityRate (INR)Amount (INR)
8683Red sand stone gang saw cut 30 mm thickMaterialsqm1.05524.00550.20
0125Mason (for plain stone work) 2nd classLabourday0.448816.00365.57
0100BandhaniLabourday0.336816.00274.18
0114BeldarLabourday0.336736.00247.30
0115CoolieLabourday0.336736.00247.30
1237Cutting marble or sand stone slab up to 50 mm thick by mechanical deviceMaterialmetre410.0040.00
9999ScaffoldingMaterialL.S.19.762.2744.86
9999Fixing including weather sealant and removingMaterialL.S.51.12.27116.00
9999Silicon gun/ pump etc.MaterialL.S.68.252.27154.93
TOTAL
2,040.34
Add 1 % Water charges on “W”
20.40
TOTAL
2,060.74
Add GST on “X” (multiplying factor 0.2127)
438.32
TOTAL
2,499.06
Add 15% CPOH on “Y”
374.86
TOTAL
2,873.92
Add Cess @ 1% on “Z”
28.74
Cost of 1 sqm
2,902.66
Say
2,902.65

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 417. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works