Skip to main content

CPWD Analysis of Rates · Cladding Work

Extra for stone work for wall lining on exterior walls of height more than 10 m from ground level for every additional height of 3 m or part there of

Item number
8.19
Analysis basis
Detail of cost for 10 sqm
Priced inputs
5
Derived rate
165.85 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 8.19 Extra for stone work for wall lining on exterior walls of height more than 10 m from ground level for every additional height of 3 m or part there of — is derived from 5 priced inputs for 10 sqm and works out to ₹165.85 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • Analysis same as Item Number 13.74
CodeInputUnitQuantityRate (INR)Amount (INR)
9999ScaffoldingMaterialL.S.215.282.27488.69
0123Mason 1st classMason 1st classLabourday0.3897.00269.10
0114BeldarLabourday0.3736.00220.80
0101BhistiLabourday0.15816.00122.40
9999SundriesMaterialL.S.28.62.2764.92
TOTAL
1,165.91
Add 1 % Water charges on “W”
11.66
TOTAL
1,177.57
Add GST on “X” (multiplying factor 0.2127)
250.47
TOTAL
1,428.04
Add 15% CPOH on “Y”
214.21
TOTAL
1,642.25
Add Cess @ 1% on “Z”
16.42
Cost of 10.00 sqm
1,658.67
Cost of 1.00 sqm
165.87
Say
165.85

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 416. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works