Skip to main content
R/DAR 2023

Stone work (machine cut edges in veneer work) for wall lining upto 10 m height, backing filled with a grout of 12 mm thick cement mortar 1:3 (1 Cement : 3 coarse sand) and jointed with Cement mortar 1:2 (1 cement : 2 stone dust), including grinding with hand grinder on joints, rubbing and polishing complete. (To be secured to the backing and the sides by means of cramps and pins which shall be paid for separately) Prepolished kota stone slabs on exposed face

25 mm thick
Item number
8.18.1.1
Analysis basis
Details of cost for 10sqm.
Priced inputs
8
Derived rate
₹2,651.35/ SQM
D-01/RATE ANALYSISITEM 8.18.1.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 8.18.1.1 (Stone work (machine cut edges in veneer work) for wall lining upto 10 m height, backing filled with a grout of 12 mm thick cement mortar 1:3 (1 Cement : 3 coarse sand) and jointed with Cement mortar 1:2 (1 cement : 2 stone dust), including grinding with hand grinder on joints, rubbing and polishing complete. (To be secured to the backing and the sides by means of cramps and pins which shall be paid for separately) Prepolished kota stone slabs on exposed face 25 mm thick) is derived from 8 priced inputs and works out to ₹2,651.35 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 25mm thick kota stone slabs = 10 sqm.
  • Total = 11.00 sqm.
  • Cement mortar 1:3 (1 cement : 3 coarse sand)
  • Add 10% wastage = 1.00 sqm.
ANALYSIS OF RATES · ITEM 8.18.1.1DETAILS OF COST FOR 10SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1168MATKotastone slab 25mm thick (Semi-Polished)Kota stone slab 20 mm to 25 mm thick (semi-polished)sq.m.11320.003,520.00
SUBRate as per Item Number 3.8 of SH: MortarsRate as per item 3.8cum0.1444,881.95703.00
9999MATCement mortar for pointing.L.S.40.432.2791.78
0125LABMason (for plain stone work) 2nd class)Mason (for plain stone work) 2nd classday6.5816.005,304.00
0114LABBeldarday6.5736.004,784.00
0115LABCoolieday4.3736.003,164.80
0139LABSkilled Beldar (for grinding with hand grinder, rubbing and polishing)Skilled Beldar (for floor rubbing etc.)day1816.00816.00
9999MATSundriesL.S.111.542.27253.20
BUILD-UP TO RATE
TOTAL
18,636.78
Add 1 % Water charges on “W
+186.37
TOTAL
18,823.15
Add GST on “X” (multiplying factor 0.2127)
+4,003.68
TOTAL
22,826.83
Add 15% CPOH on “Y
+3,424.02
TOTAL
26,250.85
Add Cess @ 1% on “Z
+262.51
Cost of 10 sqm
26,513.36
Cost of 1 sqm
2,651.34
SAY
₹2,651.35
D-02/SOURCEPRINTED PAGE 416
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
416

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 416. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSCLADDING WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.