CPWD Analysis of Rates · Cladding Work
Stone work (machine cut edges in veneer work) for wall lining upto 10 m height, backing filled with a grout of 12 mm thick cement mortar 1:3 (1 Cement : 3 coarse sand) and jointed with Cement mortar 1:2 (1 cement : 2 stone dust), including grinding with hand grinder on joints, rubbing and polishing complete. (To be secured to the backing and the sides by means of cramps and pins which shall be paid for separately) Prepolished kota stone slabs on exposed face
25 mm thick
- Item number
- 8.18.1.1
- Analysis basis
- Details of cost for 10sqm.
- Priced inputs
- 8
- Derived rate
- ₹2,651.35 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 8.18.1.1 — Stone work (machine cut edges in veneer work) for wall lining upto 10 m height, backing filled with a grout of 12 mm thick cement mortar 1:3 (1 Cement : 3 coarse sand) and jointed with Cement mortar 1:2 (1 cement : 2 stone dust), including grinding with hand grinder on joints, rubbing and polishing complete. (To be secured to the backing and the sides by means of cramps and pins which shall be paid for separately) Prepolished kota stone slabs on exposed face 25 mm thick — is derived from 8 priced inputs and works out to ₹2,651.35 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- 25mm thick kota stone slabs = 10 sqm.
- Total = 11.00 sqm.
- Cement mortar 1:3 (1 cement : 3 coarse sand)
- Add 10% wastage = 1.00 sqm.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 1168 | Kotastone slab 25mm thick (Semi-Polished)Kota stone slab 20 mm to 25 mm thick (semi-polished)Material | sq.m. | 11 | 320.00 | 3,520.00 |
| Rate as per Item Number 3.8 of SH: MortarsRate as per item 3.8Sub-analysis | cum | 0.144 | 4,881.95 | 703.00 | |
| 9999 | Cement mortar for pointing.Material | L.S. | 40.43 | 2.27 | 91.78 |
| 0125 | Mason (for plain stone work) 2nd class)Mason (for plain stone work) 2nd classLabour | day | 6.5 | 816.00 | 5,304.00 |
| 0114 | BeldarLabour | day | 6.5 | 736.00 | 4,784.00 |
| 0115 | CoolieLabour | day | 4.3 | 736.00 | 3,164.80 |
| 0139 | Skilled Beldar (for grinding with hand grinder, rubbing and polishing)Skilled Beldar (for floor rubbing etc.)Labour | day | 1 | 816.00 | 816.00 |
| 9999 | SundriesMaterial | L.S. | 111.54 | 2.27 | 253.20 |
- TOTAL
- 18,636.78
- Add 1 % Water charges on “W
- 186.37
- TOTAL
- 18,823.15
- Add GST on “X” (multiplying factor 0.2127)
- 4,003.68
- TOTAL
- 22,826.83
- Add 15% CPOH on “Y
- 3,424.02
- TOTAL
- 26,250.85
- Add Cess @ 1% on “Z
- 262.51
- Cost of 10 sqm
- 26,513.36
- Cost of 1 sqm
- 2,651.34
- Say
- 2,651.35
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 416. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works