Skip to main content
R/DAR 2023

Providing and fixing dry cladding upto 10 metre heights with 30mm thick gang saw cut stone

White sand stone - 30mm thick gang saw cut stone
Item number
8.20.2
Analysis basis
1 sqm
Priced inputs
9
Derived rate
₹3,040.10/ SQM
D-01/RATE ANALYSISITEM 8.20.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 8.20.2 (Providing and fixing dry cladding upto 10 metre heights with 30mm thick gang saw cut stone White sand stone - 30mm thick gang saw cut stone) is derived from 9 priced inputs for 1 sqm and works out to ₹3,040.10 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • White sand stone = 1.00sqm
  • Total = 1.05 sqm
  • Add 5% wastage = 0.05sqm
ANALYSIS OF RATES · ITEM 8.20.2DETAILS OF COST FOR 1 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8684MATWhite sand stone gang saw cut 30 mm thicksqm1.05616.00646.80
0125LABMason (for plain stone work) 2nd classday0.448816.00365.57
0100LABBandhaniday0.336816.00274.18
0114LABBeldarday0.336736.00247.30
0115LABCoolieday0.336736.00247.30
1237MATCutting marble or sand stone slab up to 50 mm thick by mechanical devicemetre410.0040.00
9999MATScaffoldingL.S.19.762.2744.86
9999MATFixing including weather sealant and removingL.S.51.12.27116.00
9999MATSilicon gun/ pump etc.L.S.68.252.27154.93
BUILD-UP TO RATE
TOTAL
2,136.94
Add 1 % Water charges on “W”
+21.37
TOTAL
2,158.31
Add GST on “X” (multiplying factor 0.2127)
+459.07
TOTAL
2,617.38
Add 15% CPOH on “Y”
+392.61
TOTAL
3,009.99
Add Cess @ 1% on “Z”
+30.10
Cost of 1 sqm
3,040.09
SAY
₹3,040.10
D-02/SOURCEPRINTED PAGE 417
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
417

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 417. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSCLADDING WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.