Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 8.20.2 (Providing and fixing dry cladding upto 10 metre heights with 30mm thick gang saw cut stone White sand stone - 30mm thick gang saw cut stone) is derived from 9 priced inputs for 1 sqm and works out to ₹3,040.10 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- White sand stone = 1.00sqm
- Total = 1.05 sqm
- Add 5% wastage = 0.05sqm
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 8684 | MAT | White sand stone gang saw cut 30 mm thick | sqm | 1.05 | 616.00 | 646.80 |
| 0125 | LAB | Mason (for plain stone work) 2nd class | day | 0.448 | 816.00 | 365.57 |
| 0100 | LAB | Bandhani | day | 0.336 | 816.00 | 274.18 |
| 0114 | LAB | Beldar | day | 0.336 | 736.00 | 247.30 |
| 0115 | LAB | Coolie | day | 0.336 | 736.00 | 247.30 |
| 1237 | MAT | Cutting marble or sand stone slab up to 50 mm thick by mechanical device | metre | 4 | 10.00 | 40.00 |
| 9999 | MAT | Scaffolding | L.S. | 19.76 | 2.27 | 44.86 |
| 9999 | MAT | Fixing including weather sealant and removing | L.S. | 51.1 | 2.27 | 116.00 |
| 9999 | MAT | Silicon gun/ pump etc. | L.S. | 68.25 | 2.27 | 154.93 |
- TOTAL
- 2,136.94
- Add 1 % Water charges on “W”
- +21.37
- TOTAL
- 2,158.31
- Add GST on “X” (multiplying factor 0.2127)
- +459.07
- TOTAL
- 2,617.38
- Add 15% CPOH on “Y”
- +392.61
- TOTAL
- 3,009.99
- Add Cess @ 1% on “Z”
- +30.10
- Cost of 1 sqm
- 3,040.09
- SAY
- ₹3,040.10
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 417
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 417. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.