R/DAR 2023

Providing and fixing 6 mm dia. G.I. level adjusting hangers (upto 1200mm length), fixed to roof slabs by means of ceiling cleats made out of G.I. flat 40x3mm size 60 mm long and stainless steel expandable dash fastener of 12.5 mm dia and 50 mm long, complete as per direction of Engineer-in-charge

Item number
21.6
Analysis basis
23 nos
Priced inputs
6
Derived rate
₹82.45/ NOS
D-01/RATE ANALYSISITEM 21.6

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 21.6 (Providing and fixing 6 mm dia. G.I. level adjusting hangers (upto 1200mm length), fixed to roof slabs by means of ceiling cleats made out of G.I. flat 40x3mm size 60 mm long and stainless steel expandable dash fastener of 12.5 mm dia and 50 mm long, complete as per direction of Engineer-in-charge) is derived from 6 priced inputs for 23 nos and works out to ₹82.45 each after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 2.40 m = 5.76 sqm)one number
  • 6 mm dia G.I. adjustable hangers including clips
  • (upto 1.20 metre length).
  • For light fitting 2x4 = 8.00
  • For runners = 15.00
  • Total = 23.00
  • Ceiling cleats
  • G.I. flat 40X3 mm 60mm long
  • 23x0.06 = 1.38 m @ 0.95kg/m = 1.31kg
  • Total = 1.38 kg say 0.014 q
  • Add 5% wastage = 0.07 kg
ANALYSIS OF RATES · ITEM 21.6DETAILS OF COST FOR 23 NOS (HANGERS IN 2.40 MX
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7395MAT6 mm dia. G.I. adjustable hangers including clips (upto 1.2 m length)6 mm dia G.I. adjustable hangers including clips (up to 1.2 m length)each2321.00483.00
0992MATGalvanised steel plain sheetsquintal0.0146,800.0095.20
7388MATDash hold fastener 12.5 mm dia, 40 mm long with 6 mm dia boltDash hold fastener 12.5 mm dia, 50 mm long with 6 mm dia bolteach2310.00230.00
9977MATCarriage of materialsL.S.5.22.2711.80
0111LABCarpenter 1st classday0.35897.00313.95
0114LABBeldarday0.27736.00198.72
BUILD-UP TO RATE
TOTAL
1,332.67
Add 1 % Water charges on “W”
+13.33
TOTAL
1,346.00
Add GST on “X” (multiplying factor 0.2127)
+286.29
TOTAL
1,632.29
Add 15% CPOH on “Y”
+244.84
TOTAL
1,877.13
Add Cess @ 1% on “Z”
+18.77
Cost for 23 hangers
1,895.90
Cost for one hanger
82.43
SAY
₹82.45
D-02/SOURCEPRINTED PAGE 1827
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1827

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1827. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.