CPWD Analysis of Rates · Aluminium Work
Providing and fixing 6 mm dia. G.I. level adjusting hangers (upto 1200mm length), fixed to roof slabs by means of ceiling cleats made out of G.I. flat 40x3mm size 60 mm long and stainless steel expandable dash fastener of 12.5 mm dia and 50 mm long, complete as per direction of Engineer-in-charge
- Item number
- 21.6
- Analysis basis
- Details of cost for 23 nos (hangers in 2.40 mx
- Priced inputs
- 6
- Derived rate
- ₹82.45 / nos
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 21.6 — Providing and fixing 6 mm dia. G.I. level adjusting hangers (upto 1200mm length), fixed to roof slabs by means of ceiling cleats made out of G.I. flat 40x3mm size 60 mm long and stainless steel expandable dash fastener of 12.5 mm dia and 50 mm long, complete as per direction of Engineer-in-charge — is derived from 6 priced inputs for 23 nos and works out to ₹82.45 each after water charges, GST, CPOH and cess. The full build-up is below.
- 2.40 m = 5.76 sqm)one number
- 6 mm dia G.I. adjustable hangers including clips
- (upto 1.20 metre length).
- For light fitting 2x4 = 8.00
- For runners = 15.00
- Total = 23.00
- Ceiling cleats
- G.I. flat 40X3 mm 60mm long
- 23x0.06 = 1.38 m @ 0.95kg/m = 1.31kg
- Total = 1.38 kg say 0.014 q
- Add 5% wastage = 0.07 kg
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 7395 | 6 mm dia. G.I. adjustable hangers including clips (upto 1.2 m length)6 mm dia G.I. adjustable hangers including clips (up to 1.2 m length)Material | each | 23 | 21.00 | 483.00 |
| 0992 | Galvanised steel plain sheetsMaterial | quintal | 0.014 | 6,800.00 | 95.20 |
| 7388 | Dash hold fastener 12.5 mm dia, 40 mm long with 6 mm dia boltDash hold fastener 12.5 mm dia, 50 mm long with 6 mm dia boltMaterial | each | 23 | 10.00 | 230.00 |
| 9977 | Carriage of materialsMaterial | L.S. | 5.2 | 2.27 | 11.80 |
| 0111 | Carpenter 1st classLabour | day | 0.35 | 897.00 | 313.95 |
| 0114 | BeldarLabour | day | 0.27 | 736.00 | 198.72 |
- TOTAL
- 1,332.67
- Add 1 % Water charges on “W”
- 13.33
- TOTAL
- 1,346.00
- Add GST on “X” (multiplying factor 0.2127)
- 286.29
- TOTAL
- 1,632.29
- Add 15% CPOH on “Y”
- 244.84
- TOTAL
- 1,877.13
- Add Cess @ 1% on “Z”
- 18.77
- Cost for 23 hangers
- 1,895.90
- Cost for one hanger
- 82.43
- Say
- 82.45
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1827. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.