CPWD Analysis of Rates · Aluminium Work

Providing and fixing 6 mm dia. G.I. level adjusting hangers (upto 1200mm length), fixed to roof slabs by means of ceiling cleats made out of G.I. flat 40x3mm size 60 mm long and stainless steel expandable dash fastener of 12.5 mm dia and 50 mm long, complete as per direction of Engineer-in-charge

Item number
21.6
Analysis basis
Details of cost for 23 nos (hangers in 2.40 mx
Priced inputs
6
Derived rate
82.45 / nos

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 21.6 Providing and fixing 6 mm dia. G.I. level adjusting hangers (upto 1200mm length), fixed to roof slabs by means of ceiling cleats made out of G.I. flat 40x3mm size 60 mm long and stainless steel expandable dash fastener of 12.5 mm dia and 50 mm long, complete as per direction of Engineer-in-charge — is derived from 6 priced inputs for 23 nos and works out to ₹82.45 each after water charges, GST, CPOH and cess. The full build-up is below.

  • 2.40 m = 5.76 sqm)one number
  • 6 mm dia G.I. adjustable hangers including clips
  • (upto 1.20 metre length).
  • For light fitting 2x4 = 8.00
  • For runners = 15.00
  • Total = 23.00
  • Ceiling cleats
  • G.I. flat 40X3 mm 60mm long
  • 23x0.06 = 1.38 m @ 0.95kg/m = 1.31kg
  • Total = 1.38 kg say 0.014 q
  • Add 5% wastage = 0.07 kg
CodeInputUnitQuantityRate (INR)Amount (INR)
73956 mm dia. G.I. adjustable hangers including clips (upto 1.2 m length)6 mm dia G.I. adjustable hangers including clips (up to 1.2 m length)Materialeach2321.00483.00
0992Galvanised steel plain sheetsMaterialquintal0.0146,800.0095.20
7388Dash hold fastener 12.5 mm dia, 40 mm long with 6 mm dia boltDash hold fastener 12.5 mm dia, 50 mm long with 6 mm dia boltMaterialeach2310.00230.00
9977Carriage of materialsMaterialL.S.5.22.2711.80
0111Carpenter 1st classLabourday0.35897.00313.95
0114BeldarLabourday0.27736.00198.72
TOTAL
1,332.67
Add 1 % Water charges on “W”
13.33
TOTAL
1,346.00
Add GST on “X” (multiplying factor 0.2127)
286.29
TOTAL
1,632.29
Add 15% CPOH on “Y”
244.84
TOTAL
1,877.13
Add Cess @ 1% on “Z”
18.77
Cost for 23 hangers
1,895.90
Cost for one hanger
82.43
Say
82.45

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1827. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.