Skip to main content

CPWD Analysis of Rates · Aluminium Work

Providing and fixing powder coated aluminium work (minimum thickness of powder coating 50 micron) consisting of tee/ angle sections, of approved make conforming to IS : 733 in frames of false ceiling including aluminium angle cleats with necessary C.P. brass/ stainless steel sunk screws, aluminium perimeter angles fixed to wall with stainless steel rawl plugs @ 450 mm centre to centre and fixing the frame work to G.I. level adjusting hangers 6 mm dia. with necessary cadmium plated machine screws all complete as per approved architectural drawings and direction of the Engineer-in-charge (level adjusting hangers, ceiling cleats and expansion hold fasteners to be paid for separately)

Item number
21.5
Analysis basis
Details of cost for 6.35 kg (2.40x2.40 = 5.76
Priced inputs
9
Derived rate
817.15 / kg

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 21.5 Providing and fixing powder coated aluminium work (minimum thickness of powder coating 50 micron) consisting of tee/ angle sections, of approved make conforming to IS : 733 in frames of false ceiling including aluminium angle cleats with necessary C.P. brass/ stainless steel sunk screws, aluminium perimeter angles fixed to wall with stainless steel rawl plugs @ 450 mm centre to centre and fixing the frame work to G.I. level adjusting hangers 6 mm dia. with necessary cadmium plated machine screws all complete as per approved architectural drawings and direction of the Engineer-in-charge (level adjusting hangers, ceiling cleats and expansion hold fasteners to be paid for separately) — is derived from 9 priced inputs for 6.35 kg and works out to ₹817.15 per kg after water charges, GST, CPOH and cess. The full build-up is below.

  • sqm)
  • (i) Aluminium main runner - assuming Tee of
  • size 35x23.5x1.5 mm @ 600 mm centre to
  • centre
  • 3x2.40 m = 7.20 m
  • Extra for light fittings
  • 2x1.20 m = 2.40 m
  • Total= 9.60 m @ 0.247 kg/m = 2.370 kg
  • Aluminium cross runner - assuming Tee of size
  • 35x23.5x1.5 mm @ 600 mm centre to centre
  • 3x4x0.60 m = 7.20 m
  • (-) 2x0.30 = (-) 0.60 m
  • Total=6.60 m @ 0.247 kg/m = 1.630 kg
  • Perimeter angle aluminium - assuming size
  • 25.4x25.4x1.63 mm @ 600 mm centre to centre
  • 4x2.40 m = 9.60 m @ 0.213 kg/m = 2.045 kg
  • (ii) CLEATS
  • Aluminium angle- assuming size
  • 25.4x25.4x1.63 mm
  • Extra for light fittings =3x2x2 = 12.00
  • Corner = 4.00
  • For joining runners = 42.00
  • Total = 58.00x0.025 = 1.45 m @ 0.213 kg/m =
  • 0.309 kg
  • Sub total = 2.370 + 1.630 + 2.045 + 0.309
  • =6.354 kg
  • Total = 6.672 kg
  • (iii) C.P. brass/ stainless steel screws 20 mm for
  • angle cleats=2x58 =116 Nos
  • (iv) Rawl plug for fixing perimeter angles
  • Epoxy
  • (vi)
  • (vii)
  • For fabrication and erection
  • Add 5% wastage = 0.318 kg
CodeInputUnitQuantityRate (INR)Amount (INR)
7306Aluminium T or L sectionsMaterialkilogram6.672198.001,321.06
0589Chromium plated Brass screws 20 mmMaterial100 Nos1.16152.00176.32
7048Rawl plug 50 mm (designation 10 no.)Rawl plug 50 mm (designation 10)Materialeach2424.00576.00
7392Powder coating 50 microns on aluminium sectionsMaterialkilogram6.67266.00440.35
9977Carriage of materialMaterialL.S.132.2729.51
9999C.P. brass screws for fixing frame with suspendersMaterialL.S.132.2729.51
0111Carpenter 1st classLabourday0.64897.00574.08
0114BeldarLabourday0.64736.00471.04
9999Scaffolding and sundriesMaterialL.S.132.2729.51
TOTAL
3,647.38
Add 1 % Water charges on “W”
36.47
TOTAL
3,683.85
Add GST on “X” (multiplying factor 0.2127)
783.55
TOTAL
4,467.40
Add 15% CPOH on “Y”
670.11
TOTAL
5,137.51
Add Cess @ 1% on “Z”
51.38
Cost for 6.35 kg
5,188.89
Cost for 1 kg
817.15
Say
817.15

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1826. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works