Providing and fixing powder coated aluminium work (minimum thickness of powder coating 50 micron) consisting of tee/ angle sections, of approved make conforming to IS : 733 in frames of false ceiling including aluminium angle cleats with necessary C.P. brass/ stainless steel sunk screws, aluminium perimeter angles fixed to wall with stainless steel rawl plugs @ 450 mm centre to centre and fixing the frame work to G.I. level adjusting hangers 6 mm dia. with necessary cadmium plated machine screws all complete as per approved architectural drawings and direction of the Engineer-in-charge (level adjusting hangers, ceiling cleats and expansion hold fasteners to be paid for separately)
- Item number
- 21.5
- Analysis basis
- 6.35 kg
- Priced inputs
- 9
- Derived rate
- ₹817.15/ KG
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 21.5 (Providing and fixing powder coated aluminium work (minimum thickness of powder coating 50 micron) consisting of tee/ angle sections, of approved make conforming to IS : 733 in frames of false ceiling including aluminium angle cleats with necessary C.P. brass/ stainless steel sunk screws, aluminium perimeter angles fixed to wall with stainless steel rawl plugs @ 450 mm centre to centre and fixing the frame work to G.I. level adjusting hangers 6 mm dia. with necessary cadmium plated machine screws all complete as per approved architectural drawings and direction of the Engineer-in-charge (level adjusting hangers, ceiling cleats and expansion hold fasteners to be paid for separately)) is derived from 9 priced inputs for 6.35 kg and works out to ₹817.15 per kg after water charges, GST, CPOH and cess. The full build-up is below.
- sqm)
- (i) Aluminium main runner - assuming Tee of
- size 35x23.5x1.5 mm @ 600 mm centre to
- centre
- 3x2.40 m = 7.20 m
- Extra for light fittings
- 2x1.20 m = 2.40 m
- Total= 9.60 m @ 0.247 kg/m = 2.370 kg
- Aluminium cross runner - assuming Tee of size
- 35x23.5x1.5 mm @ 600 mm centre to centre
- 3x4x0.60 m = 7.20 m
- (-) 2x0.30 = (-) 0.60 m
- Total=6.60 m @ 0.247 kg/m = 1.630 kg
- Perimeter angle aluminium - assuming size
- 25.4x25.4x1.63 mm @ 600 mm centre to centre
- 4x2.40 m = 9.60 m @ 0.213 kg/m = 2.045 kg
- (ii) CLEATS
- Aluminium angle- assuming size
- 25.4x25.4x1.63 mm
- Extra for light fittings =3x2x2 = 12.00
- Corner = 4.00
- For joining runners = 42.00
- Total = 58.00x0.025 = 1.45 m @ 0.213 kg/m =
- 0.309 kg
- Sub total = 2.370 + 1.630 + 2.045 + 0.309
- =6.354 kg
- Total = 6.672 kg
- (iii) C.P. brass/ stainless steel screws 20 mm for
- angle cleats=2x58 =116 Nos
- (iv) Rawl plug for fixing perimeter angles
- Epoxy
- (vi)
- (vii)
- For fabrication and erection
- Add 5% wastage = 0.318 kg
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 7306 | MAT | Aluminium T or L sections | kilogram | 6.672 | 198.00 | 1,321.06 |
| 0589 | MAT | Chromium plated Brass screws 20 mm | 100 Nos | 1.16 | 152.00 | 176.32 |
| 7048 | MAT | Rawl plug 50 mm (designation 10 no.)Rawl plug 50 mm (designation 10) | each | 24 | 24.00 | 576.00 |
| 7392 | MAT | Powder coating 50 microns on aluminium sections | kilogram | 6.672 | 66.00 | 440.35 |
| 9977 | MAT | Carriage of material | L.S. | 13 | 2.27 | 29.51 |
| 9999 | MAT | C.P. brass screws for fixing frame with suspenders | L.S. | 13 | 2.27 | 29.51 |
| 0111 | LAB | Carpenter 1st class | day | 0.64 | 897.00 | 574.08 |
| 0114 | LAB | Beldar | day | 0.64 | 736.00 | 471.04 |
| 9999 | MAT | Scaffolding and sundries | L.S. | 13 | 2.27 | 29.51 |
- TOTAL
- 3,647.38
- Add 1 % Water charges on “W”
- +36.47
- TOTAL
- 3,683.85
- Add GST on “X” (multiplying factor 0.2127)
- +783.55
- TOTAL
- 4,467.40
- Add 15% CPOH on “Y”
- +670.11
- TOTAL
- 5,137.51
- Add Cess @ 1% on “Z”
- +51.38
- Cost for 6.35 kg
- 5,188.89
- Cost for 1 kg
- 817.15
- SAY
- ₹817.15
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1826
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1826. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.