CPWD Analysis of Rates · Aluminium Work

Providing and fixing 12 mm thick prelaminated particle board flat pressed three layer or graded wood particle board conforming to IS: 12823 Grade l Type ll, in panelling fixed in aluminum doors, windows shutters and partition frames with C.P. brass / stainless steel screws etc. complete as per architectural drawings and directions of engineer-in-charge

Pre-laminated particle board with decorative lamination on both sides

Item number
21.2.2
Analysis basis
Details of cost for 7 sqm
Priced inputs
5
Derived rate
1,115.40 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 21.2.2 Providing and fixing 12 mm thick prelaminated particle board flat pressed three layer or graded wood particle board conforming to IS: 12823 Grade l Type ll, in panelling fixed in aluminum doors, windows shutters and partition frames with C.P. brass / stainless steel screws etc. complete as per architectural drawings and directions of engineer-in-charge Pre-laminated particle board with decorative lamination on both sides — is derived from 5 priced inputs for 7 sqm and works out to ₹1,115.40 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • 12 mm thick particle board = 7.00 sqm
  • Total = 7.35 sqm
  • Add 5% wastage = 0.35 sqm
CodeInputUnitQuantityRate (INR)Amount (INR)
7480Prelaminated particle board with both sides decorative lamination, flat pressed 3 layer & graded (medium density) Grade I, Type II conforming to IS : 12823 (exterior grade) 12 mm thickPrelaminated flat pressed three layer or graded wood particle board with both sides decorative lamination, (medium density) Grade I, Type II conforming and marked to IS : 12823 (exterior grade) 12 mm thickMaterialsqm7.35534.003,924.90
9977Carriage of particle boardMaterialL.S.13.652.2730.99
9999Sundries & screws etc.MaterialL.S.27.32.2761.97
0112Carpenter 2nd classLabourday0.9816.00734.40
0114BeldarLabourday1736.00736.00
TOTAL
5,488.26
Add 1 % Water charges on “W”
54.88
TOTAL
5,543.14
Add GST on “X” (multiplying factor 0.2127)
1,179.03
TOTAL
6,722.17
Add 15% CPOH on “Y”
1,008.33
TOTAL
7,730.50
Add Cess @ 1% on “Z”
77.31
Cost for 7 sqm
7,807.81
Cost for 1 sqm
1,115.40
Say
1,115.40

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1822. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.