Providing and fixing glazing in aluminium door, window, ventilator shutters and partitions etc. with EPDM rubber / neoprene gasket etc. complete as per the architectural drawings and the directions of engineer-in-charge . (Cost of aluminium snap beading shall be paid in basic item)

With float glass panes of 4.0 mm thickness (weight not less than 10kg/sqm)

Item number
21.3.1
Analysis basis
Details of cost for 1.00 sqm
Priced inputs
6
Derived rate
1,176.80 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 21.3.1 Providing and fixing glazing in aluminium door, window, ventilator shutters and partitions etc. with EPDM rubber / neoprene gasket etc. complete as per the architectural drawings and the directions of engineer-in-charge . (Cost of aluminium snap beading shall be paid in basic item): With float glass panes of 4.0 mm thickness (weight not less than 10kg/sqm) — is derived from 6 priced inputs for 1.00 sqm and works out to ₹1,176.80 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • Float Glass panes 4.0 mm thick = 1.00 sqm
  • sqm
  • Total =1.10 sqm
  • Add for wastage & breakage @ 10% = 0.10
CodeInputUnitQuantityRate (INR)Amount (INR)
2406Float glass sheet of nominal thickness 4 mm (weight not less than 10kg/sqm)Float glass panes of nominal thickness 4 mm (weight not less than 10 kg/sqm)Materialsqm1.1321.00353.10
9977Carriage of glassMaterialL.S.2.422.275.49
7390Neoprene/EPDM rubber gasketEPDM Gasket for uPVC window/doorMaterialmetre616.0096.00
0112Carpenter 2nd classLabourday0.23816.00187.68
0114BeldarLabourday0.23736.00169.28
9988Sundries and carriage of gasketMaterialL.S.6.892.2715.64
TOTAL
827.19
Add 1 % Water charges on “W”
8.27
TOTAL
835.46
Add GST on “X” (multiplying factor 0.2127)
177.70
TOTAL
1,013.16
Add 15% CPOH on “Y”
151.97
TOTAL
1,165.13
Add Cess @ 1% on “Z”
11.65
Cost for 1 sqm
1,176.78
Say
1,176.80

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1823. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.