CPWD Analysis of Rates · Aluminium Work
Providing and fixing 12 mm thick prelaminated particle board flat pressed three layer or graded wood particle board conforming to IS: 12823 Grade l Type ll, in panelling fixed in aluminum doors, windows shutters and partition frames with C.P. brass / stainless steel screws etc. complete as per architectural drawings and directions of engineer-in-charge
Pre-laminated particle board with decorative lamination on one side and balancing lamination on other side
- Item number
- 21.2.1
- Analysis basis
- Details of cost for 7 sqm
- Priced inputs
- 5
- Derived rate
- ₹1,139.30 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 21.2.1 — Providing and fixing 12 mm thick prelaminated particle board flat pressed three layer or graded wood particle board conforming to IS: 12823 Grade l Type ll, in panelling fixed in aluminum doors, windows shutters and partition frames with C.P. brass / stainless steel screws etc. complete as per architectural drawings and directions of engineer-in-charge Pre-laminated particle board with decorative lamination on one side and balancing lamination on other side — is derived from 5 priced inputs for 7 sqm and works out to ₹1,139.30 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- 12 mm thick particle board = 7.00 sqm
- Total = 7.35 sqm
- Add 5% wastage = 0.35 sqm
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 7477 | Prelaminated particle board with one side decorative and other side balancing lamination, flat pressed 3 layer & graded (medium density) Grade I, Type II conforming to IS : 12823 (exterior grade) 12 mm thickPrelaminated particle board with one side decorative and other side balancing lamination, flat pressed 3 layer & graded (medium density) Grade-I, Type II conforming to IS : 12823 (exterior grade) 12 mm thickMaterial | sqm | 7.35 | 550.00 | 4,042.50 |
| 9977 | Carriage of particle boardMaterial | L.S. | 13.65 | 2.27 | 30.99 |
| 9999 | Sundries & screws etc.Material | L.S. | 27.3 | 2.27 | 61.97 |
| 0112 | Carpenter 2nd classLabour | day | 0.9 | 816.00 | 734.40 |
| 0114 | BeldarLabour | day | 1 | 736.00 | 736.00 |
- TOTAL
- 5,605.86
- Add 1 % Water charges on “W”
- 56.06
- TOTAL
- 5,661.92
- Add GST on “X” (multiplying factor 0.2127)
- 1,204.29
- TOTAL
- 6,866.21
- Add 15% CPOH on “Y”
- 1,029.93
- TOTAL
- 7,896.14
- Add Cess @ 1% on “Z”
- 78.96
- Cost for 7 sqm
- 7,975.10
- Cost for 1 sqm
- 1,139.30
- Say
- 1,139.30
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1822. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.