R/DAR 2023

Filling the gap in between aluminium/ stone/ wood frame and adjacent RCC/Brick/ Stone/ wood/ Ceramic/ Gypsum work by providing weather/structural non sag elastomeric PU sealant over backer rod of approved quality as per architectural drawings and direction of Engineerin-charge complete, complying to ASTM C920, DIN 18540-F & ISO 11600

Upto 10 mm depth and 10 mm width
Item number
21.19.2
Analysis basis
10m length
Priced inputs
5
Derived rate
₹200.95/ M LENGTH
D-01/RATE ANALYSISITEM 21.19.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 21.19.2 (Filling the gap in between aluminium/ stone/ wood frame and adjacent RCC/Brick/ Stone/ wood/ Ceramic/ Gypsum work by providing weather/structural non sag elastomeric PU sealant over backer rod of approved quality as per architectural drawings and direction of Engineerin-charge complete, complying to ASTM C920, DIN 18540-F & ISO 11600 Upto 10 mm depth and 10 mm width) is derived from 5 priced inputs for 10m length and works out to ₹200.95 per m length after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • depth 10mm
ANALYSIS OF RATES · ITEM 21.19.2DETAILS OF COST FOR 10M LENGTH, WIDTH 10MM &
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
2604MATWeather/structural non sag elastomeric PU sealant (600ml Sausage) for joints in RCC/ Brick/ Stone/ wood/ Ceramic/ Gypsum/Alluminium work complying to ASTM C920, DIN 18540F & ISO 11600 incl all taxesWeather/structural non sag elastomeric PU sealant (600ml Sausage) for joints in RCC/ Brick/ Stone/ wood/ Ceramic/ Gypsum/ Alluminium work complying to ASTM C920, DIN 18540-F & ISO 11600 including all taxeseach1.5564.00846.00
8654MATMasking tapemetre202.0040.00
9999MATSundries, including charges of Sealant gun machine, dhoti etcL.S.262.2759.02
9977MATCarriage of materialL.S.8.42.2719.07
0123LABMason 1st classMason 1st classday0.5897.00448.50
BUILD-UP TO RATE
TOTAL
1,412.59
Add 1 % Water charges on “W”
+14.13
TOTAL
1,426.72
Add GST on “X” (multiplying factor 0.2127)
+303.46
TOTAL
1,730.18
Add 15% CPOH on “Y”
+259.53
TOTAL
1,989.71
Add Cess @ 1% on “Z”
+19.90
Cost of 10 metre
2,009.61
Cost per metre
200.96
SAY
₹200.95
D-02/SOURCEPRINTED PAGE 1841
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1841

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1841. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.