CPWD Analysis of Rates · Aluminium Work

Filling the gap in between aluminium/ stone/ wood frame and adjacent RCC/Brick/ Stone/ wood/ Ceramic/ Gypsum work by providing weather/structural non sag elastomeric PU sealant over backer rod of approved quality as per architectural drawings and direction of Engineerin-charge complete, complying to ASTM C920, DIN 18540-F & ISO 11600

Upto 10 mm depth and 10 mm width

Item number
21.19.2
Analysis basis
Details of cost for 10m length, width 10mm &
Priced inputs
5
Derived rate
200.95 / m length

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 21.19.2 Filling the gap in between aluminium/ stone/ wood frame and adjacent RCC/Brick/ Stone/ wood/ Ceramic/ Gypsum work by providing weather/structural non sag elastomeric PU sealant over backer rod of approved quality as per architectural drawings and direction of Engineerin-charge complete, complying to ASTM C920, DIN 18540-F & ISO 11600 Upto 10 mm depth and 10 mm width — is derived from 5 priced inputs for 10m length and works out to ₹200.95 per m length after water charges, GST, CPOH and cess. The full build-up is below.

  • depth 10mm
CodeInputUnitQuantityRate (INR)Amount (INR)
2604Weather/structural non sag elastomeric PU sealant (600ml Sausage) for joints in RCC/ Brick/ Stone/ wood/ Ceramic/ Gypsum/Alluminium work complying to ASTM C920, DIN 18540F & ISO 11600 incl all taxesWeather/structural non sag elastomeric PU sealant (600ml Sausage) for joints in RCC/ Brick/ Stone/ wood/ Ceramic/ Gypsum/ Alluminium work complying to ASTM C920, DIN 18540-F & ISO 11600 including all taxesMaterialeach1.5564.00846.00
8654Masking tapeMaterialmetre202.0040.00
9999Sundries, including charges of Sealant gun machine, dhoti etcMaterialL.S.262.2759.02
9977Carriage of materialMaterialL.S.8.42.2719.07
0123Mason 1st classMason 1st classLabourday0.5897.00448.50
TOTAL
1,412.59
Add 1 % Water charges on “W”
14.13
TOTAL
1,426.72
Add GST on “X” (multiplying factor 0.2127)
303.46
TOTAL
1,730.18
Add 15% CPOH on “Y”
259.53
TOTAL
1,989.71
Add Cess @ 1% on “Z”
19.90
Cost of 10 metre
2,009.61
Cost per metre
200.96
Say
200.95

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1841. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works