Filling the gap in between aluminium/ stone/ wood frame and adjacent RCC/Brick/ Stone/ wood/ Ceramic/ Gypsum work by providing weather/structural non sag elastomeric PU sealant over backer rod of approved quality as per architectural drawings and direction of Engineerin-charge complete, complying to ASTM C920, DIN 18540-F & ISO 11600

Upto 5 mm depth and 5 mm width
Item number
21.19.1
Analysis basis
10m length
Priced inputs
5
Derived rate
₹148.10/ M LENGTH
D-01/RATE ANALYSISITEM 21.19.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 21.19.1 (Filling the gap in between aluminium/ stone/ wood frame and adjacent RCC/Brick/ Stone/ wood/ Ceramic/ Gypsum work by providing weather/structural non sag elastomeric PU sealant over backer rod of approved quality as per architectural drawings and direction of Engineerin-charge complete, complying to ASTM C920, DIN 18540-F & ISO 11600 Upto 5 mm depth and 5 mm width) is derived from 5 priced inputs for 10m length and works out to ₹148.10 per m length after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • depth 5mm
ANALYSIS OF RATES · ITEM 21.19.1DETAILS OF COST FOR 10M LENGTH WIDTH 5MM &
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
2604MATWeather/structural non sag elastomeric PU sealant (600ml Sausage) for joints in RCC/ Brick/ Stone/ wood/ Ceramic/ Gypsum/Alluminium work complying to ASTM C920, DIN 18540F & ISO 11600 incl all taxesWeather/structural non sag elastomeric PU sealant (600ml Sausage) for joints in RCC/ Brick/ Stone/ wood/ Ceramic/ Gypsum/ Alluminium work complying to ASTM C920, DIN 18540-F & ISO 11600 including all taxeseach1564.00564.00
8654MATMasking tapemetre202.0040.00
9999MATSundries, including charges of Sealant gun machine, dhoti etcL.S.262.2759.02
9977MATCarriage of materialL.S.8.42.2719.07
0123LABMason 1st classMason 1st classday0.4897.00358.80
BUILD-UP TO RATE
TOTAL
1,040.89
Add 1 % Water charges on “W”
+10.41
TOTAL
1,051.30
Add GST on “X” (multiplying factor 0.2127)
+223.61
TOTAL
1,274.91
Add 15% CPOH on “Y”
+191.24
TOTAL
1,466.15
Add Cess @ 1% on “Z”
+14.66
Cost of 10 metre
1,480.81
Cost per metre
148.08
SAY
₹148.10
D-02/SOURCEPRINTED PAGE 1840
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1840

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1840. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSALUMINIUM WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.