Filling the gap in between aluminium/ stone/ wood frame and adjacent RCC/Brick/ Stone/ wood/ Ceramic/ Gypsum work by providing weather/structural non sag elastomeric PU sealant over backer rod of approved quality as per architectural drawings and direction of Engineerin-charge complete, complying to ASTM C920, DIN 18540-F & ISO 11600
- Item number
- 21.19.1
- Analysis basis
- 10m length
- Priced inputs
- 5
- Derived rate
- ₹148.10/ M LENGTH
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 21.19.1 (Filling the gap in between aluminium/ stone/ wood frame and adjacent RCC/Brick/ Stone/ wood/ Ceramic/ Gypsum work by providing weather/structural non sag elastomeric PU sealant over backer rod of approved quality as per architectural drawings and direction of Engineerin-charge complete, complying to ASTM C920, DIN 18540-F & ISO 11600 Upto 5 mm depth and 5 mm width) is derived from 5 priced inputs for 10m length and works out to ₹148.10 per m length after water charges, GST, CPOH and cess. The full build-up is below.
- depth 5mm
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 2604 | MAT | Weather/structural non sag elastomeric PU sealant (600ml Sausage) for joints in RCC/ Brick/ Stone/ wood/ Ceramic/ Gypsum/Alluminium work complying to ASTM C920, DIN 18540F & ISO 11600 incl all taxesWeather/structural non sag elastomeric PU sealant (600ml Sausage) for joints in RCC/ Brick/ Stone/ wood/ Ceramic/ Gypsum/ Alluminium work complying to ASTM C920, DIN 18540-F & ISO 11600 including all taxes | each | 1 | 564.00 | 564.00 |
| 8654 | MAT | Masking tape | metre | 20 | 2.00 | 40.00 |
| 9999 | MAT | Sundries, including charges of Sealant gun machine, dhoti etc | L.S. | 26 | 2.27 | 59.02 |
| 9977 | MAT | Carriage of material | L.S. | 8.4 | 2.27 | 19.07 |
| 0123 | LAB | Mason 1st classMason 1st class | day | 0.4 | 897.00 | 358.80 |
- TOTAL
- 1,040.89
- Add 1 % Water charges on “W”
- +10.41
- TOTAL
- 1,051.30
- Add GST on “X” (multiplying factor 0.2127)
- +223.61
- TOTAL
- 1,274.91
- Add 15% CPOH on “Y”
- +191.24
- TOTAL
- 1,466.15
- Add Cess @ 1% on “Z”
- +14.66
- Cost of 10 metre
- 1,480.81
- Cost per metre
- 148.08
- SAY
- ₹148.10
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1840
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1840. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate