Filling the gap in between aluminium/ stone/ wood frame and adjacent RCC/Brick/ Stone/ wood/ Ceramic/ Gypsum work by providing weather/structural non sag elastomeric PU sealant over backer rod of approved quality as per architectural drawings and direction of Engineerin-charge complete, complying to ASTM C920, DIN 18540-F & ISO 11600
Upto 5 mm depth and 5 mm width
- Item number
- 21.19.1
- Analysis basis
- Details of cost for 10m length width 5mm &
- Priced inputs
- 5
- Derived rate
- ₹148.10 / m length
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 21.19.1 — Filling the gap in between aluminium/ stone/ wood frame and adjacent RCC/Brick/ Stone/ wood/ Ceramic/ Gypsum work by providing weather/structural non sag elastomeric PU sealant over backer rod of approved quality as per architectural drawings and direction of Engineerin-charge complete, complying to ASTM C920, DIN 18540-F & ISO 11600 Upto 5 mm depth and 5 mm width — is derived from 5 priced inputs for 10m length and works out to ₹148.10 per m length after water charges, GST, CPOH and cess. The full build-up is below.
- depth 5mm
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 2604 | Weather/structural non sag elastomeric PU sealant (600ml Sausage) for joints in RCC/ Brick/ Stone/ wood/ Ceramic/ Gypsum/Alluminium work complying to ASTM C920, DIN 18540F & ISO 11600 incl all taxesWeather/structural non sag elastomeric PU sealant (600ml Sausage) for joints in RCC/ Brick/ Stone/ wood/ Ceramic/ Gypsum/ Alluminium work complying to ASTM C920, DIN 18540-F & ISO 11600 including all taxesMaterial | each | 1 | 564.00 | 564.00 |
| 8654 | Masking tapeMaterial | metre | 20 | 2.00 | 40.00 |
| 9999 | Sundries, including charges of Sealant gun machine, dhoti etcMaterial | L.S. | 26 | 2.27 | 59.02 |
| 9977 | Carriage of materialMaterial | L.S. | 8.4 | 2.27 | 19.07 |
| 0123 | Mason 1st classMason 1st classLabour | day | 0.4 | 897.00 | 358.80 |
- TOTAL
- 1,040.89
- Add 1 % Water charges on “W”
- 10.41
- TOTAL
- 1,051.30
- Add GST on “X” (multiplying factor 0.2127)
- 223.61
- TOTAL
- 1,274.91
- Add 15% CPOH on “Y”
- 191.24
- TOTAL
- 1,466.15
- Add Cess @ 1% on “Z”
- 14.66
- Cost of 10 metre
- 1,480.81
- Cost per metre
- 148.08
- Say
- 148.10
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1840. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.