Providing and fixing 12 mm thick frameless toughened glass door shutter of approved brand and manufacture, including providing and fixing top & bottom pivot & double acting hydraulic floor spring type fixing arrangement and making necessary holes etc. for fixing required door fittings, all complete as per direction of Engineer-in-charge (Door handle, lock and stopper etc.to be paid separately)
- Item number
- 21.18
- Analysis basis
- 2.10 sqm
- Priced inputs
- 7
- Derived rate
- ₹5,325.90/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 21.18 (Providing and fixing 12 mm thick frameless toughened glass door shutter of approved brand and manufacture, including providing and fixing top & bottom pivot & double acting hydraulic floor spring type fixing arrangement and making necessary holes etc. for fixing required door fittings, all complete as per direction of Engineer-in-charge (Door handle, lock and stopper etc.to be paid separately)) is derived from 7 priced inputs for 2.10 sqm and works out to ₹5,325.90 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Glass= 2.10 Sqm.
- Total= 2.31 sqm.
- Stainless steel pivot and double acting hydraulic
- floor spring type fixing
- Add Wastage @ 10% = 0.21 sqm.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 8778 | MAT | Toughened glass 12 mm thickness | sqm | 2.31 | 1,925.00 | 4,446.75 |
| 9977 | MAT | Carriage of glass panes and other materials | L.S. | 8.19 | 2.27 | 18.59 |
| 9999 | MAT | Methylated spirit | L.S. | 5.33 | 2.27 | 12.10 |
| SUB | Rate as per Item No.21.4.1 of SH:Aluminium WorkRate as per item 21.4.1 | each | 1 | 2,823.85 | 2,823.85 | |
| 0119 | LAB | Glazier | day | 0.9 | 816.00 | 734.40 |
| 0114 | LAB | Beldar | day | 0.9 | 736.00 | 662.40 |
| 9999 | MAT | Sundries,sush rog cotton etc. | L.S. | 1.13 | 2.27 | 2.57 |
- TOTAL
- 8,700.66
- Add 1 % Water charges on “W-A”
- +58.77
- TOTAL
- 8,759.43
- Add GST on “X-A” (multiplying factor 0.2127)
- +1,262.50
- TOTAL
- 10,021.93
- Add 15% CPOH on “Y-A”
- +1,079.71
- TOTAL
- 11,101.64
- Add Cess @ 1% on “Z-A”
- +82.78
- Cost for 2.10 sqm
- 11,184.42
- Cost for 1 sqm
- 5,325.91
- SAY
- ₹5,325.90
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1839
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1839. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate