Providing and fixing 12 mm thick frameless toughened glass door shutter of approved brand and manufacture, including providing and fixing top & bottom pivot & double acting hydraulic floor spring type fixing arrangement and making necessary holes etc. for fixing required door fittings, all complete as per direction of Engineer-in-charge (Door handle, lock and stopper etc.to be paid separately)

Item number
21.18
Analysis basis
Details of cost for 2.10 sqm
Priced inputs
7
Derived rate
5,325.90 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 21.18 Providing and fixing 12 mm thick frameless toughened glass door shutter of approved brand and manufacture, including providing and fixing top & bottom pivot & double acting hydraulic floor spring type fixing arrangement and making necessary holes etc. for fixing required door fittings, all complete as per direction of Engineer-in-charge (Door handle, lock and stopper etc.to be paid separately) — is derived from 7 priced inputs for 2.10 sqm and works out to ₹5,325.90 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • Glass= 2.10 Sqm.
  • Total= 2.31 sqm.
  • Stainless steel pivot and double acting hydraulic
  • floor spring type fixing
  • Add Wastage @ 10% = 0.21 sqm.
CodeInputUnitQuantityRate (INR)Amount (INR)
8778Toughened glass 12 mm thicknessMaterialsqm2.311,925.004,446.75
9977Carriage of glass panes and other materialsMaterialL.S.8.192.2718.59
9999Methylated spiritMaterialL.S.5.332.2712.10
Rate as per Item No.21.4.1 of SH:Aluminium WorkRate as per item 21.4.1Sub-analysiseach12,823.852,823.85
0119GlazierLabourday0.9816.00734.40
0114BeldarLabourday0.9736.00662.40
9999Sundries,sush rog cotton etc.MaterialL.S.1.132.272.57
TOTAL
8,700.66
Add 1 % Water charges on “W-A”
58.77
TOTAL
8,759.43
Add GST on “X-A” (multiplying factor 0.2127)
1,262.50
TOTAL
10,021.93
Add 15% CPOH on “Y-A”
1,079.71
TOTAL
11,101.64
Add Cess @ 1% on “Z-A”
82.78
Cost for 2.10 sqm
11,184.42
Cost for 1 sqm
5,325.91
Say
5,325.90

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1839. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.