CPWD Analysis of Rates · Aluminium Work
Providing and fixing 12 mm thick frameless toughened glass door shutter of approved brand and manufacture, including providing and fixing top & bottom pivot & double acting hydraulic floor spring type fixing arrangement and making necessary holes etc. for fixing required door fittings, all complete as per direction of Engineer-in-charge (Door handle, lock and stopper etc.to be paid separately)
- Item number
- 21.18
- Analysis basis
- Details of cost for 2.10 sqm
- Priced inputs
- 7
- Derived rate
- ₹5,325.90 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 21.18 — Providing and fixing 12 mm thick frameless toughened glass door shutter of approved brand and manufacture, including providing and fixing top & bottom pivot & double acting hydraulic floor spring type fixing arrangement and making necessary holes etc. for fixing required door fittings, all complete as per direction of Engineer-in-charge (Door handle, lock and stopper etc.to be paid separately) — is derived from 7 priced inputs for 2.10 sqm and works out to ₹5,325.90 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Glass= 2.10 Sqm.
- Total= 2.31 sqm.
- Stainless steel pivot and double acting hydraulic
- floor spring type fixing
- Add Wastage @ 10% = 0.21 sqm.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 8778 | Toughened glass 12 mm thicknessMaterial | sqm | 2.31 | 1,925.00 | 4,446.75 |
| 9977 | Carriage of glass panes and other materialsMaterial | L.S. | 8.19 | 2.27 | 18.59 |
| 9999 | Methylated spiritMaterial | L.S. | 5.33 | 2.27 | 12.10 |
| Rate as per Item No.21.4.1 of SH:Aluminium WorkRate as per item 21.4.1Sub-analysis | each | 1 | 2,823.85 | 2,823.85 | |
| 0119 | GlazierLabour | day | 0.9 | 816.00 | 734.40 |
| 0114 | BeldarLabour | day | 0.9 | 736.00 | 662.40 |
| 9999 | Sundries,sush rog cotton etc.Material | L.S. | 1.13 | 2.27 | 2.57 |
- TOTAL
- 8,700.66
- Add 1 % Water charges on “W-A”
- 58.77
- TOTAL
- 8,759.43
- Add GST on “X-A” (multiplying factor 0.2127)
- 1,262.50
- TOTAL
- 10,021.93
- Add 15% CPOH on “Y-A”
- 1,079.71
- TOTAL
- 11,101.64
- Add Cess @ 1% on “Z-A”
- 82.78
- Cost for 2.10 sqm
- 11,184.42
- Cost for 1 sqm
- 5,325.91
- Say
- 5,325.90
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1839. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.