Providing and fixing anodised aluminium grill (anodised transparent or dyed to required shade according to IS: 1868 with minimum anodic coating of grade AC 15) of approved design/ pattern, with approved standard section and fixed to the existing window frame with C.P. brass/ stainless steel screws @ 200 mm centre to centre, including cutting the grill to proper opening size for fixing and operation of handles and fixing approved anodised aluminium standard section around the opening, all complete as per requirement and direction of Engineer-incharge. (Only weight of grill to be measured for payment)
- Item number
- 21.17
- Analysis basis
- 10.00 kg
- Priced inputs
- 7
- Derived rate
- ₹638.35/ KG
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 21.17 (Providing and fixing anodised aluminium grill (anodised transparent or dyed to required shade according to IS: 1868 with minimum anodic coating of grade AC 15) of approved design/ pattern, with approved standard section and fixed to the existing window frame with C.P. brass/ stainless steel screws @ 200 mm centre to centre, including cutting the grill to proper opening size for fixing and operation of handles and fixing approved anodised aluminium standard section around the opening, all complete as per requirement and direction of Engineer-incharge. (Only weight of grill to be measured for payment)) is derived from 7 priced inputs for 10.00 kg and works out to ₹638.35 per kg after water charges, GST, CPOH and cess. The full build-up is below.
- Anodised aluminium grill = 10.00 kg
- for fixing
- Add 20% wastage = 2 kg = 12 kg
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 8774 | MAT | Aluminium GrillAluminium Grill as per IS 1868 | kg | 12 | 294.00 | 3,528.00 |
| 9977 | MAT | Carriage of materials | L.S. | 11 | 2.27 | 24.97 |
| 0116 | LAB | Fitter (grade 1) | day | 0.5 | 897.00 | 448.50 |
| 0139 | LAB | Skilled Beldar (for floor rubbing etc.) | day | 0.25 | 816.00 | 204.00 |
| 0114 | LAB | Beldar | day | 0.25 | 736.00 | 184.00 |
| 0100 | LAB | Bandhani | day | 0.05 | 816.00 | 40.80 |
| 9999 | MAT | Sundries | L.S. | 25 | 2.27 | 56.75 |
- TOTAL
- 4,487.02
- Add 1 % Water charges on “W”
- +44.87
- TOTAL
- 4,531.89
- Add GST on “X” (multiplying factor 0.2127)
- +963.93
- TOTAL
- 5,495.82
- Add 15% CPOH on “Y”
- +824.37
- TOTAL
- 6,320.19
- Add Cess @ 1% on “Z”
- +63.20
- Cost for 10.00 kg
- 6,383.39
- Cost for 1 kg
- 638.34
- SAY
- ₹638.35
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1839
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1839. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.