CPWD Analysis of Rates · Aluminium Work
Providing and fixing anodised aluminium grill (anodised transparent or dyed to required shade according to IS: 1868 with minimum anodic coating of grade AC 15) of approved design/ pattern, with approved standard section and fixed to the existing window frame with C.P. brass/ stainless steel screws @ 200 mm centre to centre, including cutting the grill to proper opening size for fixing and operation of handles and fixing approved anodised aluminium standard section around the opening, all complete as per requirement and direction of Engineer-incharge. (Only weight of grill to be measured for payment)
- Item number
- 21.17
- Analysis basis
- Details of cost for 10.00 kg
- Priced inputs
- 7
- Derived rate
- ₹638.35 / kg
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 21.17 — Providing and fixing anodised aluminium grill (anodised transparent or dyed to required shade according to IS: 1868 with minimum anodic coating of grade AC 15) of approved design/ pattern, with approved standard section and fixed to the existing window frame with C.P. brass/ stainless steel screws @ 200 mm centre to centre, including cutting the grill to proper opening size for fixing and operation of handles and fixing approved anodised aluminium standard section around the opening, all complete as per requirement and direction of Engineer-incharge. (Only weight of grill to be measured for payment) — is derived from 7 priced inputs for 10.00 kg and works out to ₹638.35 per kg after water charges, GST, CPOH and cess. The full build-up is below.
- Anodised aluminium grill = 10.00 kg
- for fixing
- Add 20% wastage = 2 kg = 12 kg
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 8774 | Aluminium GrillAluminium Grill as per IS 1868Material | kg | 12 | 294.00 | 3,528.00 |
| 9977 | Carriage of materialsMaterial | L.S. | 11 | 2.27 | 24.97 |
| 0116 | Fitter (grade 1)Labour | day | 0.5 | 897.00 | 448.50 |
| 0139 | Skilled Beldar (for floor rubbing etc.)Labour | day | 0.25 | 816.00 | 204.00 |
| 0114 | BeldarLabour | day | 0.25 | 736.00 | 184.00 |
| 0100 | BandhaniLabour | day | 0.05 | 816.00 | 40.80 |
| 9999 | SundriesMaterial | L.S. | 25 | 2.27 | 56.75 |
- TOTAL
- 4,487.02
- Add 1 % Water charges on “W”
- 44.87
- TOTAL
- 4,531.89
- Add GST on “X” (multiplying factor 0.2127)
- 963.93
- TOTAL
- 5,495.82
- Add 15% CPOH on “Y”
- 824.37
- TOTAL
- 6,320.19
- Add Cess @ 1% on “Z”
- 63.20
- Cost for 10.00 kg
- 6,383.39
- Cost for 1 kg
- 638.34
- Say
- 638.35
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1839. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.