Filling the gap in between aluminium/ stone/ wood frame and adjacent RCC/Brick/ Stone/ wood/ Ceramic/ Gypsum work by providing weather/structural non sag elastomeric PU sealant over backer rod of approved quality as per architectural drawings and direction of Engineerin-charge complete, complying to ASTM C920, DIN 18540-F & ISO 11600
- Item number
- 21.19.3
- Analysis basis
- 10m length
- Priced inputs
- 6
- Derived rate
- ₹363.20/ M LENGTH
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 21.19.3 (Filling the gap in between aluminium/ stone/ wood frame and adjacent RCC/Brick/ Stone/ wood/ Ceramic/ Gypsum work by providing weather/structural non sag elastomeric PU sealant over backer rod of approved quality as per architectural drawings and direction of Engineerin-charge complete, complying to ASTM C920, DIN 18540-F & ISO 11600 Upto 20 mm depth and 20 mm width) is derived from 6 priced inputs for 10m length and works out to ₹363.20 per m length after water charges, GST, CPOH and cess. The full build-up is below.
- depth 20mm
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 2604 | MAT | Weather/structural non sag elastomeric PU sealant (600ml Sausage) for joints in RCC/ Brick/ Stone/ wood/ Ceramic/ Gypsum/Alluminium work complying to ASTM C920, DIN 18540F & ISO 11600 incl all taxesWeather/structural non sag elastomeric PU sealant (600ml Sausage) for joints in RCC/ Brick/ Stone/ wood/ Ceramic/ Gypsum/ Alluminium work complying to ASTM C920, DIN 18540-F & ISO 11600 including all taxes | each | 3 | 564.00 | 1,692.00 |
| 8654 | MAT | Masking tape | metre | 20 | 2.00 | 40.00 |
| 2630 | MAT | Baker rod | metre | 10 | 7.00 | 70.00 |
| 9999 | MAT | Sundries, including charges of Sealant gun machine, dhoti etc | L.S. | 26 | 2.27 | 59.02 |
| 9977 | MAT | Carriage of material | L.S. | 8.4 | 2.27 | 19.07 |
| 0123 | LAB | Mason 1st classMason 1st class | day | 0.75 | 897.00 | 672.75 |
- TOTAL
- 2,552.84
- Add 1 % Water charges on “W”
- +25.53
- TOTAL
- 2,578.37
- Add GST on “X” (multiplying factor 0.2127)
- +548.42
- TOTAL
- 3,126.79
- Add 15% CPOH on “Y”
- +469.02
- TOTAL
- 3,595.81
- Add Cess @ 1% on “Z”
- +35.96
- Cost of 10 metre
- 3,631.77
- Cost per metre
- 363.18
- SAY
- ₹363.20
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1841
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1841. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.