CPWD Analysis of Rates · Aluminium Work
Providing and fixing anodised aluminium (anodised transparent or dyed to required shade according to IS: 1868. Minimum anodic coating of grade AC 15) sub frame work for windows and ventilators with extruded built up standard tubular sections of approved make conforming to IS: 733 and IS: 1285, fixed with dash fastener of required dia and size (Dash fastener to be paid for separately)
- Item number
- 21.14
- Analysis basis
- Details of cost for 4.082kg
- Priced inputs
- 9
- Derived rate
- ₹402.80
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 21.14 — Providing and fixing anodised aluminium (anodised transparent or dyed to required shade according to IS: 1868. Minimum anodic coating of grade AC 15) sub frame work for windows and ventilators with extruded built up standard tubular sections of approved make conforming to IS: 733 and IS: 1285, fixed with dash fastener of required dia and size (Dash fastener to be paid for separately) — is derived from 9 priced inputs and works out to ₹402.80 after water charges, GST, CPOH and cess. The full build-up is below.
- Aluminium Section
- (i) External member of the frame (Jindal section
- no TU/ 3644)
- V = 2x2.00 = 4.00 m
- H = 2x1.20 = 2.40 m
- Total= 6.40 m @ 0.607 kg/m = 3.885kg
- Angle cleat 38x38x4.8 mm 50 mm long
- 4x0.05 = 0.200 m @ 0.985 kg/m = 0.197 kg
- sub total = 4.082kg.
- Total = 4.286kg
- For fabrication of frame
- Add 5% wastage = 0.204kg
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 7306 | Aluminium T or L sectionsMaterial | kilogram | 4.286 | 198.00 | 848.63 |
| 0589 | Chromium plated Brass screws 20 mmMaterial | 100 Nos | 0.08 | 152.00 | 12.16 |
| 7389 | Anodising 15 microns on aluminium sectionsMaterial | kilogram | 4.286 | 42.00 | 180.01 |
| 9977 | Carriage of materialMaterial | L.S. | 5.2 | 2.27 | 11.80 |
| 0116 | Fitter (grade 1)Labour | day | 0.04 | 897.00 | 35.88 |
| 0139 | Skilled Beldar (for floor rubbing etc.)Labour | day | 0.04 | 816.00 | 32.64 |
| 0114 | BeldarLabour | day | 0.02 | 736.00 | 14.72 |
| 0100 | BandhaniLabour | day | 0.01 | 816.00 | 8.16 |
| 9999 | Labour for drilling holes, hire charges of drill, electricity charges, carriage of dash hold fastners & sundriesMaterial | L.S. | 5.2 | 2.27 | 11.80 |
- TOTAL
- 1,155.80
- Add 1 % Water charges on “W”
- 11.56
- TOTAL
- 1,167.36
- Add GST on “X” (multiplying factor 0.2127)
- 248.30
- TOTAL
- 1,415.66
- Add 15% CPOH on “Y”
- 212.35
- TOTAL
- 1,628.01
- Add Cess @ 1% on “Z”
- 16.28
- Cost for 4.082 kg
- 1,644.29
- Cost for 1 kg
- 402.81
- Say
- 402.80
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1835. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.