Providing and fixing anodised aluminium (anodised transparent or dyed to required shade according to IS: 1868. Minimum anodic coating of grade AC 15) sub frame work for windows and ventilators with extruded built up standard tubular sections of approved make conforming to IS: 733 and IS: 1285, fixed with dash fastener of required dia and size (Dash fastener to be paid for separately)

Item number
21.14
Analysis basis
Details of cost for 4.082kg
Priced inputs
9
Derived rate
₹402.80
D-01/RATE ANALYSISITEM 21.14

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 21.14 (Providing and fixing anodised aluminium (anodised transparent or dyed to required shade according to IS: 1868. Minimum anodic coating of grade AC 15) sub frame work for windows and ventilators with extruded built up standard tubular sections of approved make conforming to IS: 733 and IS: 1285, fixed with dash fastener of required dia and size (Dash fastener to be paid for separately)) is derived from 9 priced inputs and works out to ₹402.80 after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Aluminium Section
  • (i) External member of the frame (Jindal section
  • no TU/ 3644)
  • V = 2x2.00 = 4.00 m
  • H = 2x1.20 = 2.40 m
  • Total= 6.40 m @ 0.607 kg/m = 3.885kg
  • Angle cleat 38x38x4.8 mm 50 mm long
  • 4x0.05 = 0.200 m @ 0.985 kg/m = 0.197 kg
  • sub total = 4.082kg.
  • Total = 4.286kg
  • For fabrication of frame
  • Add 5% wastage = 0.204kg
ANALYSIS OF RATES · ITEM 21.14DETAILS OF COST FOR 4.082KG
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7306MATAluminium T or L sectionskilogram4.286198.00848.63
0589MATChromium plated Brass screws 20 mm100 Nos0.08152.0012.16
7389MATAnodising 15 microns on aluminium sectionskilogram4.28642.00180.01
9977MATCarriage of materialL.S.5.22.2711.80
0116LABFitter (grade 1)day0.04897.0035.88
0139LABSkilled Beldar (for floor rubbing etc.)day0.04816.0032.64
0114LABBeldarday0.02736.0014.72
0100LABBandhaniday0.01816.008.16
9999MATLabour for drilling holes, hire charges of drill, electricity charges, carriage of dash hold fastners & sundriesL.S.5.22.2711.80
BUILD-UP TO RATE
TOTAL
1,155.80
Add 1 % Water charges on “W”
+11.56
TOTAL
1,167.36
Add GST on “X” (multiplying factor 0.2127)
+248.30
TOTAL
1,415.66
Add 15% CPOH on “Y”
+212.35
TOTAL
1,628.01
Add Cess @ 1% on “Z”
+16.28
Cost for 4.082 kg
1,644.29
Cost for 1 kg
402.81
SAY
₹402.80
D-02/SOURCEPRINTED PAGE 1835
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1835

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1835. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSALUMINIUM WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.