Providing and fixing aluminium casement windows fastener of required length for aluminium windows with necessary screws etc. complete

Anodized (AC 15) aluminium
Item number
21.15.1
Analysis basis
10 nos
Priced inputs
4
Derived rate
₹89.40/ NOS
D-01/RATE ANALYSISITEM 21.15.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 21.15.1 (Providing and fixing aluminium casement windows fastener of required length for aluminium windows with necessary screws etc. complete Anodized (AC 15) aluminium) is derived from 4 priced inputs for 10 nos and works out to ₹89.40 each after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 21.15.1DETAIL OF COST FOR 10 NOS
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8660MATAluminium casement window fastener (Anodised AC 15)each1055.00550.00
8666MATStainless steel screws 25 mm x4 mm100 Nos0.446.0018.40
0111LABCarpenter 1st classday0.06897.0053.82
9977MATCarriage of materialsL.S.2.732.276.20
BUILD-UP TO RATE
TOTAL
628.42
Add 1 % Water charges on “W”
+6.28
TOTAL
634.70
Add GST on “X” (multiplying factor 0.2127)
+135.00
TOTAL
769.70
Add 15% CPOH on “Y”
+115.46
TOTAL
885.16
Add Cess @ 1% on “Z”
+8.85
Cost of 10 nos
894.01
Cost of 1 nos
89.40
SAY
₹89.40
D-02/SOURCEPRINTED PAGE 1836
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1836

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1836. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.