Providing and fixing Brass 100mm mortice latch and lock with 6 levers without pair of handles (best make of approved quality) for aluminium doors including necessary cutting and making good etc. complete

Item number
21.13
Analysis basis
1 nos
Priced inputs
3
Derived rate
₹528.85/ NO
D-01/RATE ANALYSISITEM 21.13

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 21.13 (Providing and fixing Brass 100mm mortice latch and lock with 6 levers without pair of handles (best make of approved quality) for aluminium doors including necessary cutting and making good etc. complete) is derived from 3 priced inputs for 1 nos and works out to ₹528.85 per no after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 21.13DETAIL OF COST FOR 1 NOS
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7001MATBrass 100mm mortice latch and lock with 6 levers without pair of handlesBrass 100 mm mortice latch and lock with 6 levers without pair of handleseach1211.00211.00
0111LABCarpenter 1st classday0.17897.00152.49
9999MATSundry and screwsL.S.3.642.278.26
BUILD-UP TO RATE
TOTAL
371.75
Add 1 % Water charges on “W”
+3.72
TOTAL
375.47
Add GST on “X” (multiplying factor 0.2127)
+79.86
TOTAL
455.33
Add 15% CPOH on “Y”
+68.30
TOTAL
523.63
Add Cess @ 1% on “Z”
+5.24
Cost of 1 no
528.87
SAY
₹528.85
D-02/SOURCEPRINTED PAGE 1835
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1835

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1835. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSALUMINIUM WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.