Providing and fixing aluminium tubular handle bar 32 mm outer dia, 3.0 mm thick & 2100 mm long with SS screws etc .complete as per direction of Engineer-in-Charge
- Item number
- 21.12.3
- Analysis basis
- 10 nos
- Priced inputs
- 5
- Derived rate
- ₹645.50/ NO
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 21.12.3 (Providing and fixing aluminium tubular handle bar 32 mm outer dia, 3.0 mm thick & 2100 mm long with SS screws etc .complete as per direction of Engineer-in-Charge Polyester powder coated minimum thickness 50 micron aluminium tubular handle bar) is derived from 5 priced inputs for 10 nos and works out to ₹645.50 per no after water charges, GST, CPOH and cess. The full build-up is below.
- 10x22/7 x 1/4 (0.032x0.032 -0.026 x 0.026) x
- 2.10 = 0.0057 cum
- 0.0057 cum @ 2710 kg/ cum = 15.56kg
- Total = 16.34 kg
- Add 5% wastage 0.78 kg
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 7306 | MAT | Aluminium T or L sections | kilogram | 16.34 | 198.00 | 3,235.32 |
| 7393 | MAT | Polyester powder coating 50 microns on aluminium sections | kilogram | 16.34 | 72.00 | 1,176.48 |
| 9977 | MAT | Carriage of material | L.S. | 4.42 | 2.27 | 10.03 |
| 8647 | MAT | Stainless steel screws 30 mm x4 mm | 100 nos | 0.08 | 42.00 | 3.36 |
| 0111 | LAB | Carpenter 1st class | day | 0.125 | 897.00 | 112.13 |
- TOTAL
- 4,537.32
- Add 1 % Water charges on “W”
- +45.37
- TOTAL
- 4,582.69
- Add GST on “X” (multiplying factor 0.2127)
- +974.74
- TOTAL
- 5,557.43
- Add 15% CPOH on “Y”
- +833.61
- TOTAL
- 6,391.04
- Add Cess @ 1% on “Z”
- +63.91
- Cost of 10 nos
- 6,454.95
- Cost of 1 no
- 645.50
- SAY
- ₹645.50
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1834
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1834. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.