CPWD Analysis of Rates · Aluminium Work

Providing and fixing aluminium work for doors, windows, ventilators and partitions with extruded built up standard tubular sections/ appropriate Z sections and other sections of approved make conforming to IS: 733 and IS: 1285, fixing with dash fasteners of required dia and size, including necessary filling up the gaps at junctions, i.e. at top, bottom and sides with required EPDM rubber/ neoprene gasket etc. Aluminium sections shall be smooth, rust free, straight, mitred and jointed mechanically wherever required including cleat angle, Aluminium snap beading for glazing / paneling, C.P. brass / stainless steel screws, all complete as per architectural drawings and the directions of Engineer-in-charge. (Glazing, paneling and dash fasteners to be paid for separately) : For shutters of doors, windows & ventilators including providing and fixing hinges/ pivots and making provision for fixing of fittings wherever required including the cost of EPDM rubber / neoprene gasket required (Fittings shall be paid for separately)

Powder coated aluminium (minimum thickness of powder coating 50 micron)

Item number
21.1.2.2
Analysis basis
Details of cost for 20.62 kg
Priced inputs
13
Derived rate
634.45 / kg

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 21.1.2.2 Providing and fixing aluminium work for doors, windows, ventilators and partitions with extruded built up standard tubular sections/ appropriate Z sections and other sections of approved make conforming to IS: 733 and IS: 1285, fixing with dash fasteners of required dia and size, including necessary filling up the gaps at junctions, i.e. at top, bottom and sides with required EPDM rubber/ neoprene gasket etc. Aluminium sections shall be smooth, rust free, straight, mitred and jointed mechanically wherever required including cleat angle, Aluminium snap beading for glazing / paneling, C.P. brass / stainless steel screws, all complete as per architectural drawings and the directions of Engineer-in-charge. (Glazing, paneling and dash fasteners to be paid for separately) : For shutters of doors, windows & ventilators including providing and fixing hinges/ pivots and making provision for fixing of fittings wherever required including the cost of EPDM rubber / neoprene gasket required (Fittings shall be paid for separately) Powder coated aluminium (minimum thickness of powder coating 50 micron) — is derived from 13 priced inputs for 20.62 kg and works out to ₹634.45 per kg after water charges, GST, CPOH and cess. The full build-up is below.

  • (i) Hanging style (Jindal section no 4524)
  • 1x2.35 = 2.35 m @ 2.53 kg/m = 5.95 kg
  • (ii) Meeting style (Jindal section no 4526)
  • 1x2.35 = 2.35 m @ 2.465 kg/m = 5.79 kg
  • (iii) Top & bottom rail (Jindal section no 4510)
  • 2x0.75 = 1.50 m @ 2.48 kg/m = 3.72 kg
  • (iv) Lock rail (Jindal section no 4524)
  • 1x0.75 = 0.75 m @ 2.53 kg/m = 1.90 kg
  • (v) Glazing plate (Jindal section no 440) on one
  • side of lock rail
  • 1x0.75 = 0.75 m @ 0.459 kg/m = 0.34 kg
  • (vi) Aluminium snap beading (Jindal section no
  • 4497) on both side
  • 2x2 (0.75+1.26) = 8.04 m
  • 2x2 (0.75+0.81) = 6.24 m
  • = 14.28 m @ 0.176 kg/m = 2.51 kg
  • (vii) Aluminium angle cleat 38x38x4.8 mm 35
  • mm long
  • 3x4x0.035 = 0.42 m @ 0.985 kg/m = 0.41 kg
  • Sub total = 20.62 kg
  • Total = 21.65 kg
  • (viii)
  • (ix) C.P. brass /stainless steel screws 20 mm
  • For cleat 12x4 = 48
  • For Hinges 4x8 = 32
  • For glazing plate @ 15 cm centre to centre
  • in 75 cm length 2x6 = 12
  • Total = 92 Nos
  • (x) Epoxy
  • (xi)
  • (xii) Neoprene/ EPDM rubber gasket in groove
  • of meeting style
  • For fixing the shutter including hinges :
  • Add 5% wastage = 1.03 kg
CodeInputUnitQuantityRate (INR)Amount (INR)
7306Aluminium T or L sectionsMaterialkilogram21.65198.004,286.70
0689Anodised Aluminium butt hinges 100x75x4 mmMaterial10 Nos0.4410.00164.00
0589Chromium plated Brass screws 20 mmMaterial100 Nos0.92152.00139.84
7392Powder coating 50 microns on aluminium sectionsMaterialkilogram21.6566.001,428.90
9977Carriage of materialMaterialL.S.31.22.2770.82
7390Neoprene/EPDM rubber gasketEPDM Gasket for uPVC window/doorMaterialmetre2.3516.0037.60
0116Fitter (grade 1)Labourday1897.00897.00
0139Skilled Beldar (for floor rubbing etc.)Labourday1816.00816.00
0114BeldarLabourday0.5736.00368.00
0100BandhaniLabourday0.4816.00326.40
0111Carpenter 1st classLabourday0.2897.00179.40
0114BeldarLabourday0.5736.00368.00
9999Labour for making provision for fittings and carriage of screws etc. including sundriesMaterialL.S.502.27113.50
TOTAL
9,196.16
Add 1 % Water charges on “W”
91.96
TOTAL
9,288.12
Add GST on “X” (multiplying factor 0.2127)
1,975.58
TOTAL
11,263.70
Add 15% CPOH on “Y”
1,689.56
TOTAL
12,953.26
Add Cess @ 1% on “Z”
129.53
Cost for 20.62 kg
13,082.79
Cost for 1 kg
634.47
Say
634.45

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1819. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.