CPWD Analysis of Rates · Aluminium Work

Providing and fixing aluminium work for doors, windows, ventilators and partitions with extruded built up standard tubular sections/ appropriate Z sections and other sections of approved make conforming to IS: 733 and IS: 1285, fixing with dash fasteners of required dia and size, including necessary filling up the gaps at junctions, i.e. at top, bottom and sides with required EPDM rubber/ neoprene gasket etc. Aluminium sections shall be smooth, rust free, straight, mitred and jointed mechanically wherever required including cleat angle, Aluminium snap beading for glazing / paneling, C.P. brass / stainless steel screws, all complete as per architectural drawings and the directions of Engineer-in-charge. (Glazing, paneling and dash fasteners to be paid for separately) : For fixed portion

Polyester powder coated aluminium (minimum thickness of polyester powder coating 50 micron)

Item number
21.1.1.3
Analysis basis
Details of cost for 40.02 kg
Priced inputs
9
Derived rate
539.85 / kg

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 21.1.1.3 Providing and fixing aluminium work for doors, windows, ventilators and partitions with extruded built up standard tubular sections/ appropriate Z sections and other sections of approved make conforming to IS: 733 and IS: 1285, fixing with dash fasteners of required dia and size, including necessary filling up the gaps at junctions, i.e. at top, bottom and sides with required EPDM rubber/ neoprene gasket etc. Aluminium sections shall be smooth, rust free, straight, mitred and jointed mechanically wherever required including cleat angle, Aluminium snap beading for glazing / paneling, C.P. brass / stainless steel screws, all complete as per architectural drawings and the directions of Engineer-in-charge. (Glazing, paneling and dash fasteners to be paid for separately) : For fixed portion Polyester powder coated aluminium (minimum thickness of polyester powder coating 50 micron) — is derived from 9 priced inputs for 40.02 kg and works out to ₹539.85 per kg after water charges, GST, CPOH and cess. The full build-up is below.

  • (i) External member of the frame (Jindal section
  • no 4605)
  • V = 2x2.40 = 4.80 m
  • H = 2x3x0.95 = 5.70 m
  • = 10.50 m @ 1.653 kg/m = 17.36 kg
  • (ii) Internal member of the frame (Jindal section
  • no 4604)
  • V = 2x2.40 = 4.80 m
  • H = 1x3x0.95 = 2.85 m
  • = 7.65 m @ 1.692 kg/m = 12.94 kg
  • (iii) Aluminium snap beading on both side (Jindal section no 4407)
  • 2x6x2 (1.14+0.95) = 50.16 m
  • Snap beading = 50.16 m @ 0.176 kg/m = 8.33
  • kg
  • (iv) Angle cleat 38x38x4.8 mm 50 mm long
  • 18x0.05 = 0.900 m @ 0.985 kg/m = 0.89 kg
  • Sub total =40.02 kg
  • Total = 42.02 kg
  • (v) C.P. brass /stainless steel screws 20 mm for
  • cleat angle 18x4 = 72 Nos
  • (vi)
  • (vii)
  • For fabrication of frame
  • Add 5% wastage = 2.00 kg
CodeInputUnitQuantityRate (INR)Amount (INR)
7306Aluminium T or L sectionsMaterialkilogram42.02198.008,319.96
0589Chromium plated Brass screws 20 mmMaterial100 Nos0.72152.00109.44
7393Polyester powder coating 50 microns on aluminium sectionsMaterialkilogram42.0272.003,025.44
9977Carriage of materialMaterialL.S.522.27118.04
0116Fitter (grade 1)Labourday2897.001,794.00
0139Skilled Beldar (for floor rubbing etc.)Labourday1816.00816.00
0114BeldarLabourday1736.00736.00
0100BandhaniLabourday0.05816.0040.80
9999Labour for drilling holes, hire charges of drill, electricity charges, carriage of dash hold fastners and sundriesMaterialL.S.1002.27227.00
TOTAL
15,186.68
Add 1 % Water charges on “W”
151.87
TOTAL
15,338.55
Add GST on “X” (multiplying factor 0.2127)
3,262.51
TOTAL
18,601.06
Add 15% CPOH on “Y”
2,790.16
TOTAL
21,391.22
Add Cess @ 1% on “Z”
213.91
Cost for 40.02 kg
21,605.13
Cost for 1 kg
539.86
Say
539.85

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1817. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works