CPWD Analysis of Rates · Aluminium Work
Providing and fixing aluminium work for doors, windows, ventilators and partitions with extruded built up standard tubular sections/ appropriate Z sections and other sections of approved make conforming to IS: 733 and IS: 1285, fixing with dash fasteners of required dia and size, including necessary filling up the gaps at junctions, i.e. at top, bottom and sides with required EPDM rubber/ neoprene gasket etc. Aluminium sections shall be smooth, rust free, straight, mitred and jointed mechanically wherever required including cleat angle, Aluminium snap beading for glazing / paneling, C.P. brass / stainless steel screws, all complete as per architectural drawings and the directions of Engineer-in-charge. (Glazing, paneling and dash fasteners to be paid for separately) : For fixed portion
Powder coated aluminium (minimum thickness of powder coating 50 micron)
- Item number
- 21.1.1.2
- Analysis basis
- Details of cost for 40.02 kg
- Priced inputs
- 9
- Derived rate
- ₹530.90 / kg
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 21.1.1.2 — Providing and fixing aluminium work for doors, windows, ventilators and partitions with extruded built up standard tubular sections/ appropriate Z sections and other sections of approved make conforming to IS: 733 and IS: 1285, fixing with dash fasteners of required dia and size, including necessary filling up the gaps at junctions, i.e. at top, bottom and sides with required EPDM rubber/ neoprene gasket etc. Aluminium sections shall be smooth, rust free, straight, mitred and jointed mechanically wherever required including cleat angle, Aluminium snap beading for glazing / paneling, C.P. brass / stainless steel screws, all complete as per architectural drawings and the directions of Engineer-in-charge. (Glazing, paneling and dash fasteners to be paid for separately) : For fixed portion Powder coated aluminium (minimum thickness of powder coating 50 micron) — is derived from 9 priced inputs for 40.02 kg and works out to ₹530.90 per kg after water charges, GST, CPOH and cess. The full build-up is below.
- (i) External member of the frame (Jindal section
- no 4605)
- V = 2x2.40 = 4.80 m
- H = 2x3x0.95 = 5.70 m
- = 10.50 m @ 1.653 kg/m = 17.36 kg
- (ii) Internal member of the frame (Jindal section
- no 4604)
- V = 2x2.40 = 4.80 m
- H = 1x3x0.95 = 2.85 m
- = 7.65 m @ 1.692 kg/m = 12.94 kg
- (iii) Aluminium snap beading on both side (Jindal section no 4407)
- 2x6x2 (1.14+0.95) = 50.16 m
- Snap beading = 50.16 m @ 0.176 kg/m
- = 8.33 kg
- (iv) Angle cleat 38x38x4.8 mm 50 mm long
- 18x0.05 = 0.900 m @ 0.985 kg/m = 0.89 kg
- Sub total =40.02 kg
- Total = 42.02 kg
- (v) C.P. brass /stainless steel screws 20 mm for
- cleat angle 18x4 = 72 Nos
- (vi) Epoxy
- (vii)
- For fabrication of frame
- Add 5% wastage = 2.00 kg
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 7306 | Aluminium T or L sectionsMaterial | kilogram | 42.02 | 198.00 | 8,319.96 |
| 0589 | Chromium plated Brass screws 20 mmMaterial | 100 Nos | 0.72 | 152.00 | 109.44 |
| 7392 | Powder coating 50 microns on aluminium sectionsMaterial | kilogram | 42.02 | 66.00 | 2,773.32 |
| 9977 | Carriage of materialMaterial | L.S. | 52 | 2.27 | 118.04 |
| 0116 | Fitter (grade 1)Labour | day | 2 | 897.00 | 1,794.00 |
| 0139 | Skilled Beldar (for floor rubbing etc.)Labour | day | 1 | 816.00 | 816.00 |
| 0114 | BeldarLabour | day | 1 | 736.00 | 736.00 |
| 0100 | BandhaniLabour | day | 0.05 | 816.00 | 40.80 |
| 9999 | Labour for drilling holes, hire charges of drill, electricity charges, carriage of dash hold fastners and sundriesMaterial | L.S. | 100 | 2.27 | 227.00 |
- TOTAL
- 14,934.56
- Add 1 % Water charges on “W”
- 149.35
- TOTAL
- 15,083.91
- Add GST on “X” (multiplying factor 0.2127)
- 3,208.35
- TOTAL
- 18,292.26
- Add 15% CPOH on “Y”
- 2,743.84
- TOTAL
- 21,036.10
- Add Cess @ 1% on “Z”
- 210.36
- Cost for 40.02 kg
- 21,246.46
- Cost for 1 kg
- 530.90
- Say
- 530.90
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1816. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works