Providing and fixing aluminium work for doors, windows, ventilators and partitions with extruded built up standard tubular sections/ appropriate Z sections and other sections of approved make conforming to IS: 733 and IS: 1285, fixing with dash fasteners of required dia and size, including necessary filling up the gaps at junctions, i.e. at top, bottom and sides with required EPDM rubber/ neoprene gasket etc. Aluminium sections shall be smooth, rust free, straight, mitred and jointed mechanically wherever required including cleat angle, Aluminium snap beading for glazing / paneling, C.P. brass / stainless steel screws, all complete as per architectural drawings and the directions of Engineer-in-charge. (Glazing, paneling and dash fasteners to be paid for separately) : For fixed portion
- Item number
- 21.1.1.1
- Analysis basis
- 40.02 kg
- Priced inputs
- 9
- Derived rate
- ₹495.05/ KG
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 21.1.1.1 (Providing and fixing aluminium work for doors, windows, ventilators and partitions with extruded built up standard tubular sections/ appropriate Z sections and other sections of approved make conforming to IS: 733 and IS: 1285, fixing with dash fasteners of required dia and size, including necessary filling up the gaps at junctions, i.e. at top, bottom and sides with required EPDM rubber/ neoprene gasket etc. Aluminium sections shall be smooth, rust free, straight, mitred and jointed mechanically wherever required including cleat angle, Aluminium snap beading for glazing / paneling, C.P. brass / stainless steel screws, all complete as per architectural drawings and the directions of Engineer-in-charge. (Glazing, paneling and dash fasteners to be paid for separately) : For fixed portion Anodised aluminium (anodised transparent or dyed to required shade according to IS: 1868, Minimum anodic coating of grade AC 15)) is derived from 9 priced inputs for 40.02 kg and works out to ₹495.05 per kg after water charges, GST, CPOH and cess. The full build-up is below.
- (i) External member of the frame (Jindal section
- no 4605)
- V = 2x2.40 = 4.80 m
- H = 2x3x0.95 = 5.70 m
- = 10.50 m @ 1.653 kg/m = 17.36 kg
- (ii) Internal member of the frame (Jindal section
- no 4604)
- V = 2x2.40 = 4.80 m
- H = 1x3x0.95 = 2.85 m
- = 7.65 m @ 1.692 kg/m = 12.94 kg
- (iii) Aluminium snap beading on both side (Jindal section no 4407)
- 2x6x2 (1.14+0.95) = 50.16 m
- Snap beading = 50.16 m @ 0.176 kg/m = 8.33
- kg
- (iv) Angle cleat 38x38x4.8 mm 50 mm long
- 18x0.05 = 0.900 m @ 0.985 kg/m = 0.89 kg
- Sub total =40.02 kg
- Total = 42.02 kg
- (v) C.P. brass /stainless steel screws 20 mm for
- cleat angle 18x4 = 72 Nos
- (vi)
- (vii)
- For fabrication of frame
- Add 5% wastage = 2.00 kg
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 7306 | MAT | Aluminium T or L sections | kilogram | 42.02 | 198.00 | 8,319.96 |
| 0589 | MAT | Chromium plated Brass screws 20 mm | 100 Nos | 0.72 | 152.00 | 109.44 |
| 7389 | MAT | Anodising 15 microns on aluminium sections | kilogram | 42.02 | 42.00 | 1,764.84 |
| 9977 | MAT | Carriage of material | L.S. | 52 | 2.27 | 118.04 |
| 0116 | LAB | Fitter (grade 1) | day | 2 | 897.00 | 1,794.00 |
| 0139 | LAB | Skilled Beldar (for floor rubbing etc.) | day | 1 | 816.00 | 816.00 |
| 0114 | LAB | Beldar | day | 1 | 736.00 | 736.00 |
| 0100 | LAB | Bandhani | day | 0.05 | 816.00 | 40.80 |
| 9999 | MAT | Labour for drilling holes, hire charges of drill, electricity charges, carriage of dash hold fastners and sundries | L.S. | 100 | 2.27 | 227.00 |
- TOTAL
- 13,926.08
- Add 1 % Water charges on “W”
- +139.26
- TOTAL
- 14,065.34
- Add GST on “X” (multiplying factor 0.2127)
- +2,991.70
- TOTAL
- 17,057.04
- Add 15% CPOH on “Y”
- +2,558.56
- TOTAL
- 19,615.60
- Add Cess @ 1% on “Z”
- +196.16
- Cost for 40.02 kg
- 19,811.76
- Cost for 1 kg
- 495.05
- SAY
- ₹495.05
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1815
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1815. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.