Skip to main content
R/DAR 2023

Providing and fixing ISI marked aluminium butt hinges anodised (anodic coating not less than grade AC 10 as per IS: 1868) transparent or dyed to required colour or shade with necessary screws etc. complete

100x63x3.2 mm
Item number
9.95.5
Analysis basis
10 nos
Priced inputs
5
Derived rate
₹96.90/ NO
D-01/RATE ANALYSISITEM 9.95.5

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.95.5 (Providing and fixing ISI marked aluminium butt hinges anodised (anodic coating not less than grade AC 10 as per IS: 1868) transparent or dyed to required colour or shade with necessary screws etc. complete: 100x63x3.2 mm) is derived from 5 priced inputs for 10 nos and works out to ₹96.90 per no after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 9.95.5DETAILS OF COST FOR 10 NOS
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0690MATAnodised Aluminium butt hinges 100x63x3.2 mm10 Nos1280.00280.00
0586MATChromium plated Brass screws 40 mm100 Nos0.8254.00203.20
9977MATCarriage of materialsL.S.2.732.276.20
0111LABCarpenter 1st classday0.14897.00125.58
0114LABBeldarday0.09736.0066.24
BUILD-UP TO RATE
TOTAL
681.22
Add 1 % Water charges on “W”
+6.81
TOTAL
688.03
Add GST on “X” (multiplying factor 0.2127)
+146.34
TOTAL
834.37
Add 15% CPOH on “Y”
+125.16
TOTAL
959.53
Add Cess @ 1% on “Z”
+9.60
Cost of 10 nos.
969.13
Cost of 1 no.
96.91
SAY
₹96.90
D-02/SOURCEPRINTED PAGE 563
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
563

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 563. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWOOD AND PVC WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.