CPWD Analysis of Rates · Wood and PVC Work

Providing and fixing bright finished brass casement window fastener with necessary screws etc. complete

Item number
9.85
Analysis basis
Details of cost for 10 nos.
Priced inputs
4
Derived rate
89.00 / no

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.85 Providing and fixing bright finished brass casement window fastener with necessary screws etc. complete — is derived from 4 priced inputs for 10 nos and works out to ₹89.00 per no after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
0423Brass casement window fastenerMaterialEach1049.00490.00
0452Brass screws 25 mmMaterial100 Nos0.4110.0044.00
9977Carriage of materialMaterialL.S.0.912.272.07
0111Carpenter 1st classLabourday0.1897.0089.70
TOTAL
625.77
Add 1 % Water charges on “W”
6.26
TOTAL
632.03
Add GST on “X” (multiplying factor 0.2127)
134.43
TOTAL
766.46
Add 15% CPOH on “Y”
114.97
TOTAL
881.43
Add Cess @ 1% on “Z”
8.81
Cost of 10 nos
890.24
Cost of 1 no
89.02
Say
89.00

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 550. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works