Providing and fixing bright finished brass casement window fastener with necessary screws etc. complete

Item number
9.85
Analysis basis
10 nos
Priced inputs
4
Derived rate
₹89.00/ NO
D-01/RATE ANALYSISITEM 9.85

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.85 (Providing and fixing bright finished brass casement window fastener with necessary screws etc. complete) is derived from 4 priced inputs for 10 nos and works out to ₹89.00 per no after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 9.85DETAILS OF COST FOR 10 NOS
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0423MATBrass casement window fastenerEach1049.00490.00
0452MATBrass screws 25 mm100 Nos0.4110.0044.00
9977MATCarriage of materialL.S.0.912.272.07
0111LABCarpenter 1st classday0.1897.0089.70
BUILD-UP TO RATE
TOTAL
625.77
Add 1 % Water charges on “W”
+6.26
TOTAL
632.03
Add GST on “X” (multiplying factor 0.2127)
+134.43
TOTAL
766.46
Add 15% CPOH on “Y”
+114.97
TOTAL
881.43
Add Cess @ 1% on “Z”
+8.81
Cost of 10 nos
890.24
Cost of 1 no
89.02
SAY
₹89.00
D-02/SOURCEPRINTED PAGE 550
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
550

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 550. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWOOD AND PVC WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.