Providing and fixing aluminium die cast body tubular type universal hydraulic door closer (having brand logo with ISI, IS : 3564, embossed on the body, door weight upto 35 kg and door width upto 700 mm), with necessary accessories and screws etc. complete

Item number
9.83
Analysis basis
10 nos
Priced inputs
4
Derived rate
₹1,124.85/ NO
D-01/RATE ANALYSISITEM 9.83

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.83 (Providing and fixing aluminium die cast body tubular type universal hydraulic door closer (having brand logo with ISI, IS : 3564, embossed on the body, door weight upto 35 kg and door width upto 700 mm), with necessary accessories and screws etc. complete) is derived from 4 priced inputs for 10 nos and works out to ₹1,124.85 per no after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 9.83DETAILS OF COST FOR 10 NOS
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
2456MATHydraulic door closer bottle type M.S. body with necessary accessories and screws completeeach10699.006,990.00
0451MATBrass screws 30 mm100 Nos0.6154.0092.40
9977MATCarriage of materialL.S.3.642.278.26
0112LABCarpenter 2nd classday1816.00816.00
BUILD-UP TO RATE
TOTAL
7,906.66
Add 1 % Water charges on “W”
+79.07
TOTAL
7,985.73
Add GST on “X” (multiplying factor 0.2127)
+1,698.56
TOTAL
9,684.29
Add 15% CPOH on “Y”
+1,452.64
TOTAL
11,136.93
Add Cess @ 1% on “Z”
+111.37
Cost of 10 nos
11,248.30
Cost of 1 no
1,124.83
SAY
₹1,124.85
D-02/SOURCEPRINTED PAGE 549
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
549

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 549. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.