Providing and fixing bright finished brass parliamentary hinges with necessary screws etc. complete
- Item number
- 9.73.4
- Analysis basis
- 10 nos
- Priced inputs
- 5
- Derived rate
- ₹339.20/ NO
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.73.4 (Providing and fixing bright finished brass parliamentary hinges with necessary screws etc. complete : 75x100x20x3.2 mm) is derived from 5 priced inputs for 10 nos and works out to ₹339.20 per no after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0388 | MAT | Brass parliamentary hinges 75x100x20x3.2 mm | 10 Nos | 1 | 2,057.00 | 2,057.00 |
| 0451 | MAT | Brass screws 30 mm | 100 Nos | 0.6 | 154.00 | 92.40 |
| 9977 | MAT | Carriage of materials | L.S. | 2.73 | 2.27 | 6.20 |
| 0111 | LAB | Carpenter 1st class | day | 0.14 | 897.00 | 125.58 |
| 0114 | LAB | Beldar | day | 0.14 | 736.00 | 103.04 |
- TOTAL
- 2,384.22
- Add 1 % Water charges on “W”
- +23.84
- TOTAL
- 2,408.06
- Add GST on “X” (multiplying factor 0.2127)
- +512.19
- TOTAL
- 2,920.25
- Add 15% CPOH on “Y”
- +438.04
- TOTAL
- 3,358.29
- Add Cess @ 1% on “Z”
- +33.58
- Cost of 10 nos.
- 3,391.87
- Cost of 1 no
- 339.19
- SAY
- ₹339.20
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 540
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 540. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate