Skip to main content
R/DAR 2023

Providing and fixing bright finished brass parliamentary hinges with necessary screws etc. complete

100x125x27x5 mm
Item number
9.73.3
Analysis basis
10 nos
Priced inputs
5
Derived rate
₹381.75/ NO
D-01/RATE ANALYSISITEM 9.73.3

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.73.3 (Providing and fixing bright finished brass parliamentary hinges with necessary screws etc. complete : 100x125x27x5 mm) is derived from 5 priced inputs for 10 nos and works out to ₹381.75 per no after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 9.73.3DETAILS OF COST FOR 10 NOS
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0387MATBrass parliamentary hinges 100x125x27x5 mm10 Nos12,299.002,299.00
0450MATBrass screws 40 mm100 Nos0.8187.00149.60
9977MATCarriage of materialsL.S.2.732.276.20
0111LABCarpenter 1st classday0.14897.00125.58
0114LABBeldarday0.14736.00103.04
BUILD-UP TO RATE
TOTAL
2,683.42
Add 1 % Water charges on “W”
+26.83
TOTAL
2,710.25
Add GST on “X” (multiplying factor 0.2127)
+576.47
TOTAL
3,286.72
Add 15% CPOH on “Y”
+493.01
TOTAL
3,779.73
Add Cess @ 1% on “Z”
+37.80
Cost of 10 nos.
3,817.53
Cost of 1 no
381.75
SAY
₹381.75
D-02/SOURCEPRINTED PAGE 539
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
539

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 539. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWOOD AND PVC WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.