Providing and fixing IS : 12817 marked stainless steel butt hinges with stainless steel screws etc. complete
- Item number
- 9.70.2
- Analysis basis
- 10 nos
- Priced inputs
- 5
- Derived rate
- ₹107.10/ NO
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.70.2 (Providing and fixing IS : 12817 marked stainless steel butt hinges with stainless steel screws etc. complete : 100X58X1.90 mm) is derived from 5 priced inputs for 10 nos and works out to ₹107.10 per no after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 8216 | MAT | Stainless steel butt hinges 100x58x1.9 mm IS : 12817 marked | 10 Nos | 1 | 350.00 | 350.00 |
| 8211 | MAT | Stainless steel screws 40 mm | 100 Nos | 0.8 | 270.00 | 216.00 |
| 9977 | MAT | Carriage of materials | L.S. | 2.73 | 2.27 | 6.20 |
| 0112 | LAB | Carpenter 2nd class | day | 0.14 | 816.00 | 114.24 |
| 0114 | LAB | Beldar | day | 0.09 | 736.00 | 66.24 |
- TOTAL
- 752.68
- Add 1 % Water charges on “W”
- +7.53
- TOTAL
- 760.21
- Add GST on “X” (multiplying factor 0.2127)
- +161.70
- TOTAL
- 921.91
- Add 15% CPOH on “Y”
- +138.29
- TOTAL
- 1,060.20
- Add Cess @ 1% on “Z”
- +10.60
- Cost of 10 nos.
- 1,070.80
- Cost of 1 no
- 107.08
- SAY
- ₹107.10
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 532
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 532. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.