CPWD Analysis of Rates · Wood and PVC Work

Providing and fixing panelling or panelling and glazing in panelled or panelled and glazed shutters for doors, windows and clerestory windows (Area of opening for panel inserts excluding portion inside grooves or rebates to be measured). Panelling for panelled or panelled and glazed shutters 25 mm to 40 mm thick

Second class teak wood

Item number
9.7.1
Analysis basis
Details of cost for shutters of a door with 2/3rd
Priced inputs
3
Derived rate
3,323.20 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.7.1 Providing and fixing panelling or panelling and glazing in panelled or panelled and glazed shutters for doors, windows and clerestory windows (Area of opening for panel inserts excluding portion inside grooves or rebates to be measured). Panelling for panelled or panelled and glazed shutters 25 mm to 40 mm thick : Second class teak wood — is derived from 3 priced inputs for shutters of and works out to ₹3,323.20 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • panelling 200x108cm = 2.16sqm.
  • Panel area = 4x45.1x36.55cm = 0.66 sqm
  • Panels
  • 4x47.2x38.65x1.6cm = 0.0117cum+
  • = 0.0129 cum.
  • Add for wastage @ 10% = 0.0012cum.
CodeInputUnitQuantityRate (INR)Amount (INR)
1190Second class teak wood in planksMaterial10 cudm1.29791.001,020.39
0111Carpenter 1st classLabourday0.57897.00511.29
9999SundriesMaterialL.S.4.422.2710.03
TOTAL
1,541.71
Add 1 % Water charges on “W”
15.42
TOTAL
1,557.13
Add GST on “X” (multiplying factor 0.2127)
331.20
TOTAL
1,888.33
Add 15% CPOH on “Y”
283.25
TOTAL
2,171.58
Add Cess @ 1% on “Z”
21.72
Cost of 0.66 sqm.
2,193.30
Cost of 1 sqm.
3,323.18
Say
3,323.20

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 447. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.