CPWD Analysis of Rates · Wood and PVC Work

Providing and fixing oxidised M.S. Safety chain with necessary fixtures for doors, (weighting not less than 450 gms) and Copper oxidised as per IS 1378

Item number
9.69
Analysis basis
Details of cost for 10 nos.
Priced inputs
4
Derived rate
100.60 / no

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.69 Providing and fixing oxidised M.S. Safety chain with necessary fixtures for doors, (weighting not less than 450 gms) and Copper oxidised as per IS 1378 — is derived from 4 priced inputs for 10 nos and works out to ₹100.60 per no after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
7184Oxidised M.S. safety chain (weighing not less than 450 gms) for doorMaterialeach1060.00600.00
0685Oxidised mild steel screws 25 mmMaterial100 Nos0.639.0023.40
9977Carriage of materialsMaterialL.S.0.912.272.07
0112Carpenter 2nd classLabourday0.1816.0081.60
TOTAL
707.07
Add 1 % Water charges on “W”
7.07
TOTAL
714.14
Add GST on “X” (multiplying factor 0.2127)
151.90
TOTAL
866.04
Add 15% CPOH on “Y”
129.91
TOTAL
995.95
Add Cess @ 1% on “Z”
9.96
Cost of 10 nos.
1,005.91
Cost of 1 no.
100.59
Say
100.60

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 531. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.