Skip to main content
R/DAR 2023

Providing and fixing oxidised M.S. casement stays (straight peg type) with necessary screws etc. complete (Copper oxidised as per IS 1378)

250 mm weighing not less than 280 grams
Item number
9.68.2
Analysis basis
10 nos
Priced inputs
4
Derived rate
₹61.05/ NO
D-01/RATE ANALYSISITEM 9.68.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.68.2 (Providing and fixing oxidised M.S. casement stays (straight peg type) with necessary screws etc. complete (Copper oxidised as per IS 1378) 250 mm weighing not less than 280 grams) is derived from 4 priced inputs for 10 nos and works out to ₹61.05 per no after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 9.68.2DETAILS OF COST FOR 10 NOS
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7064MATOxidised M.S.casement stay (straight peg type) 250 mm not less than 280 kgOxidised M.S.casement stay (straight peg type) 250 mm not less than 0.28 kgeach1033.00330.00
0685MATOxidised mild steel screws 25 mm100 Nos0.439.0015.60
9977MATCarriage of materialsL.S.0.912.272.07
0112LABCarpenter 2nd classday0.1816.0081.60
BUILD-UP TO RATE
TOTAL
429.27
Add 1 % Water charges on “W”
+4.29
TOTAL
433.56
Add GST on “X” (multiplying factor 0.2127)
+92.22
TOTAL
525.78
Add 15% CPOH on “Y”
+78.87
TOTAL
604.65
Add Cess @ 1% on “Z”
+6.05
Cost of 10 nos.
610.70
Cost of 1 no.
61.07
SAY
₹61.05
D-02/SOURCEPRINTED PAGE 530
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
530

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 530. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWOOD AND PVC WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.