R/DAR 2023

Providing and fixing oxidised M.S. casement stays (straight peg type) with necessary screws etc. complete (Copper oxidised as per IS 1378)

300 mm weighing not less than 330 grams
Item number
9.68.1
Analysis basis
10 nos
Priced inputs
4
Derived rate
₹67.40/ NO
D-01/RATE ANALYSISITEM 9.68.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.68.1 (Providing and fixing oxidised M.S. casement stays (straight peg type) with necessary screws etc. complete (Copper oxidised as per IS 1378) 300 mm weighing not less than 330 grams) is derived from 4 priced inputs for 10 nos and works out to ₹67.40 per no after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 9.68.1DETAILS OF COST FOR 10 NOS
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7063MATOxidised M.S.casement stay (straight peg type) 300 mm not less than 330 gmOxidised M.S.casement stay (straight peg type) 300 mm not less than 0.33 kgeach1037.00370.00
0684MATOxidised mild steel screws 30 mm100 Nos0.450.0020.00
9977MATCarriage of materialsL.S.0.912.272.07
0112LABCarpenter 2nd classday0.1816.0081.60
BUILD-UP TO RATE
TOTAL
473.67
Add 1 % Water charges on “W”
+4.74
TOTAL
478.41
Add GST on “X” (multiplying factor 0.2127)
+101.76
TOTAL
580.17
Add 15% CPOH on “Y”
+87.03
TOTAL
667.20
Add Cess @ 1% on “Z”
+6.67
Cost of 10 nos.
673.87
Cost of 1 no.
67.39
SAY
₹67.40
D-02/SOURCEPRINTED PAGE 529
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
529

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 529. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.