Providing and fixing ISI marked oxidised M.S. handles conforming to IS:4992 with necessary screws etc. complete (Copper oxidised as per IS 1378)
- Item number
- 9.66.3
- Analysis basis
- 10 nos
- Priced inputs
- 4
- Derived rate
- ₹29.70/ NO
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.66.3 (Providing and fixing ISI marked oxidised M.S. handles conforming to IS:4992 with necessary screws etc. complete (Copper oxidised as per IS 1378) 75 mm) is derived from 4 priced inputs for 10 nos and works out to ₹29.70 per no after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0670 | MAT | Oxidised mild steel handles75 mmOxidised mild steel handles 75 mm | each | 10 | 14.00 | 140.00 |
| 0685 | MAT | Oxidised mild steel screws 25 mm | 100 Nos | 0.4 | 39.00 | 15.60 |
| 9977 | MAT | Carriage of materials | L.S. | 1.82 | 2.27 | 4.13 |
| 0112 | LAB | Carpenter 2nd class | day | 0.06 | 816.00 | 48.96 |
- TOTAL
- 208.69
- Add 1 % Water charges on “W”
- +2.09
- TOTAL
- 210.78
- Add GST on “X” (multiplying factor 0.2127)
- +44.83
- TOTAL
- 255.61
- Add 15% CPOH on “Y”
- +38.34
- TOTAL
- 293.95
- Add Cess @ 1% on “Z”
- +2.94
- Cost of 10 nos.
- 296.89
- Cost of 1 no.
- 29.69
- SAY
- ₹29.70
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 527
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 527. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.