Providing and fixing ISI marked IS:1341 M.S. pressed butt hinges bright finished with necessary screws etc. complete
- Item number
- 9.55.4
- Analysis basis
- ten hinges
- Priced inputs
- 4
- Derived rate
- ₹18.85/ NO
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.55.4 (Providing and fixing ISI marked IS:1341 M.S. pressed butt hinges bright finished with necessary screws etc. complete : 50x37x1.50 mm) is derived from 4 priced inputs for ten hinges and works out to ₹18.85 per no after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0597 | MAT | Bright finished or black enamelled ISI marked IS: 1341 mild steel pressed butt hinges50x37x1.50 mmBright finished or black enameled ISI marked IS:1341 mild steel pressed butt hinges 50x37x 1.50 mm | 10 Nos | 1 | 49.00 | 49.00 |
| 0640 | MAT | Bright finished or black enamelled mild steel screws 20 mmBright finished or black enameled mild steel screws 20 mm | 100 Nos | 0.4 | 40.00 | 16.00 |
| 9977 | MAT | Carriage of materials | L.S. | 0.91 | 2.27 | 2.07 |
| 0112 | LAB | Carpenter 2nd class | day | 0.08 | 816.00 | 65.28 |
- TOTAL
- 132.35
- Add 1 % Water charges on “W”
- +1.32
- TOTAL
- 133.67
- Add GST on “X” (multiplying factor 0.2127)
- +28.43
- TOTAL
- 162.10
- Add 15% CPOH on “Y”
- +24.32
- TOTAL
- 186.42
- Add Cess @ 1% on “Z”
- +1.86
- Cost of 10 nos.
- 188.28
- Cost of 1 no
- 18.83
- SAY
- ₹18.85
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 511
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 511. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.