Providing laminated veneer lumber conforming to IS:14616 and TAD -15: 2001 (Part B) in factory made frames of doors, windows, clerestory windows and other frames, wrought framed and fixing in position with hold fast lugs or with dash fasteners of required dia & length (hold fast lugs or dash fastener shall be paid for separately)

Item number
9.2
Analysis basis
Chowkhat of
Priced inputs
4
Derived rate
₹1,31,981.10/ CUM
D-01/RATE ANALYSISITEM 9.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.2 (Providing laminated veneer lumber conforming to IS:14616 and TAD -15: 2001 (Part B) in factory made frames of doors, windows, clerestory windows and other frames, wrought framed and fixing in position with hold fast lugs or with dash fasteners of required dia & length (hold fast lugs or dash fastener shall be paid for separately)) is derived from 4 priced inputs for Chowkhat of and works out to ₹1,31,981.10 per cum after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 206.75x117.5cm.
  • (36 cudm)
  • Laminated veneer lumber including wastage @
  • 5%
  • 2x206.75x9.5x7.0cm =0.028cum+
  • 1x117.5x9.5x7.0cm = 0.008cum. = 0.036cum.+
  • Grand Total = 0.038cum = 38cudm
  • Add for wastage @ 5% = 0.002cum.
ANALYSIS OF RATES · ITEM 9.2DETAILS OF COST FOR CHOWKHAT OF A DOOR
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7157MATLaminated veneer lumber conforming to TADS 15:1995 manufactured in factory in frames of doors, windows10 cudm3.8750.002,850.00
0111LABCarpenter 1st classday0.2897.00179.40
0112LABCarpenter 2nd classday0.2816.00163.20
0114LABBeldarday0.2736.00147.20
BUILD-UP TO RATE
TOTAL
3,339.80
Add 1 % Water charges on “W”
+33.40
TOTAL
3,373.20
Add GST on “X” (multiplying factor 0.2127)
+717.48
TOTAL
4,090.68
Add 15% CPOH on “Y”
+613.60
TOTAL
4,704.28
Add Cess @ 1% on “Z”
+47.04
Cost of 36 cudm
4,751.32
Cost of 1 cum
1,31,981.11
SAY
₹1,31,981.10
D-02/SOURCEPRINTED PAGE 437
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
437

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 437. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWOOD AND PVC WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.