CPWD Analysis of Rates · Wood and PVC Work
Providing laminated veneer lumber conforming to IS:14616 and TAD -15: 2001 (Part B) in factory made frames of doors, windows, clerestory windows and other frames, wrought framed and fixing in position with hold fast lugs or with dash fasteners of required dia & length (hold fast lugs or dash fastener shall be paid for separately)
- Item number
- 9.2
- Analysis basis
- Details of cost for Chowkhat of a door
- Priced inputs
- 4
- Derived rate
- ₹1,31,981.10 / cum
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.2 — Providing laminated veneer lumber conforming to IS:14616 and TAD -15: 2001 (Part B) in factory made frames of doors, windows, clerestory windows and other frames, wrought framed and fixing in position with hold fast lugs or with dash fasteners of required dia & length (hold fast lugs or dash fastener shall be paid for separately) — is derived from 4 priced inputs for Chowkhat of and works out to ₹1,31,981.10 per cum after water charges, GST, CPOH and cess. The full build-up is below.
- 206.75x117.5cm.
- (36 cudm)
- Laminated veneer lumber including wastage @
- 5%
- 2x206.75x9.5x7.0cm =0.028cum+
- 1x117.5x9.5x7.0cm = 0.008cum. = 0.036cum.+
- Grand Total = 0.038cum = 38cudm
- Add for wastage @ 5% = 0.002cum.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 7157 | Laminated veneer lumber conforming to TADS 15:1995 manufactured in factory in frames of doors, windowsMaterial | 10 cudm | 3.8 | 750.00 | 2,850.00 |
| 0111 | Carpenter 1st classLabour | day | 0.2 | 897.00 | 179.40 |
| 0112 | Carpenter 2nd classLabour | day | 0.2 | 816.00 | 163.20 |
| 0114 | BeldarLabour | day | 0.2 | 736.00 | 147.20 |
- TOTAL
- 3,339.80
- Add 1 % Water charges on “W”
- 33.40
- TOTAL
- 3,373.20
- Add GST on “X” (multiplying factor 0.2127)
- 717.48
- TOTAL
- 4,090.68
- Add 15% CPOH on “Y”
- 613.60
- TOTAL
- 4,704.28
- Add Cess @ 1% on “Z”
- 47.04
- Cost of 36 cudm
- 4,751.32
- Cost of 1 cum
- 1,31,981.11
- Say
- 1,31,981.10
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 437. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works