- ₹43.80/ METRE
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.174 (Providing and fixing 2mm thick 16 to 19mm wide PVC edge binding tape of approved quality for cupboard/wardrobe shutters including necessary synthetic resin hot pressed to edges on binding machine etc. complete as per directions of Engineerin-charge) is derived from 4 priced inputs for 10 metre and works out to ₹43.80 per metre after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 2489 | MAT | PVC edge binding tapePVC edge bending tape 2.00 mm thick | metre | 10 | 22.00 | 220.00 |
| 9977 | MAT | Carriage of materials | L.S. | 2.73 | 2.27 | 6.20 |
| 0111 | LAB | Carpenter 1st class | day | 0.05 | 897.00 | 44.85 |
| 0114 | LAB | Beldar | day | 0.05 | 736.00 | 36.80 |
- TOTAL
- 307.85
- Add 1 % Water charges on “W”
- +3.08
- TOTAL
- 310.93
- Add GST on “X” (multiplying factor 0.2127)
- +66.13
- TOTAL
- 377.06
- Add 15% CPOH on “Y”
- +56.56
- TOTAL
- 433.62
- Add Cess @ 1% on “Z”
- +4.34
- Cost of 10metre
- 437.96
- Cost of 1 metre
- 43.80
- SAY
- ₹43.80
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 710
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 710. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.