CPWD Analysis of Rates · Wood and PVC Work
Providing and fixing flat pressed three layer particle or graded plain wood board medium density exterior grade (Grade I) FPT-I, conforming and marked to frame, backing or studding with screws etc. complete (Frames, backing or studding to be paid separately)
12 mm thick
- Item number
- 9.17.1
- Analysis basis
- Details of cost for 350x200cm = 7sqm.
- Priced inputs
- 5
- Derived rate
- ₹802.95 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.17.1 — Providing and fixing flat pressed three layer particle or graded plain wood board medium density exterior grade (Grade I) FPT-I, conforming and marked to frame, backing or studding with screws etc. complete (Frames, backing or studding to be paid separately): 12 mm thick — is derived from 5 priced inputs and works out to ₹802.95 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- 12mm thick particle board = 7.00sqm.+ Add
- wastage @ 5% = 0.35 sqm. Total = 7.35 sqm
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0341 | Flat pressed three layer or graded particle board (medium density) exterior grade (Grade I) FPT-I :12 mm thickFlat pressed three layer or graded wood particle board (medium density) exterior grade Grade 1, FPT-1, conforming and marked to IS:3087 12 mm thickMaterial | sqm | 7.35 | 325.00 | 2,388.75 |
| 9977 | Carriage of particle boardMaterial | L.S. | 13.52 | 2.27 | 30.69 |
| 9999 | Sundries and screwsMaterial | L.S. | 26.91 | 2.27 | 61.09 |
| 0112 | Carpenter 2nd classLabour | day | 0.9 | 816.00 | 734.40 |
| 0114 | BeldarLabour | day | 1 | 736.00 | 736.00 |
- TOTAL
- 3,950.93
- Add 1 % Water charges on “W”
- 39.51
- TOTAL
- 3,990.44
- Add GST on “X” (multiplying factor 0.2127)
- 848.77
- TOTAL
- 4,839.21
- Add 15% CPOH on “Y”
- 725.88
- TOTAL
- 5,565.09
- Add Cess @ 1% on “Z”
- 55.65
- Cost of 7 sqm.
- 5,620.74
- Cost of 1 sqm.
- 802.96
- Say
- 802.95
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 470. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.